ORN1 MAINTENANCE MANAGEMENT FOR DISTRICT ENGINEERS 3rd edition (2003)


Publications with the same themes

View all

PDF content (text-only)

OVERSEAS ROAD NOTE 1 Road maintenance management for district engineers TRL Limited, Crowthorne, Berkshire, United Kingdom Road maintenance management for district engineers TRL LimitedDepartment for International Development Old Wokingham Road 1 Palace Street Crowthorne, Berkshire, RG45 6AU London, SW1E 5HE ORN 1 Overseas Road Note 1 ii First published 1981 Reprinted with minor revisions 1983 Second edition 1987 Third edition 2003 ISSN 0951-8797 Copyright TRL Limited 2003. This document is an output from a project funded by the UK Department for International Development (DFID) for the benefit of developing countries. The views expressed are not necessarily those of the DFID. TRL is committed to optimising energy efficiency, reducing waste and promoting recycling and re-use. In support of these environmental goals, this report has been printed on recycled paper, comprising 100% post-consumer waste, manufactured using a TCF (totally chlorine free) process. Subsector: Transport Theme:T2 Project title : Overseas Road Note 1: Maintenance Management for Regional and District Engineers Project reference: R7781 iii The Department for International Development: a brief mission statement The Department for International Development (DFID) is the UK Governme nt department responsible for promoting sustainable development and reducing poverty. The central focus of the Government’s policy, based on the 1997 and 2000 White Papers on I nternational Development, is a commitment to the internationally agreed Millennium De velopment Goals, to be achieved by 2015. These seek to:  Eradicate extreme poverty and hunger  Achieve universal primary education  Promote gender equality and empower women  Reduce child mortality  Improve maternal health  Combat HIV/AIDS, malaria and other diseases  Ensure environmental sustainability  Develop a global partnership for development DFID’s assistance is concentrated in the poorest countries of sub-Sah aran Africa and Asia, but also contributes to poverty reduction and sustainable development in mid dle-income countries, including those in Latin America and Eastern Europe. DFID works in partnership with governments committed to the Millennium D evelopment Goals, with civil society, the private sector and the research community. It al so works with multilateral institutions, including the World Bank, United Nations agencies, and the European Commission. DFID has headquarters in London and East Kilbride, offices in many devel oping countries, and staff based in British embassies and high commissions around the world. DFID, 1 Palace Street, London SW1E 5HE DFID, Abercrombie House, Eaglesham Road, East Kilbride, Glasgow G75 8EA Tel: +44 (0) 20 7023 0000 Fax: +44 (0) 20 7023 0019 Public Enquiry Point: 0845 300 4100 (from outside the UK: +44 1355 84 3 132) DFID website: www.dfid.gov.uk Email: enquiry@dfid.gov.uk iv ACKNOWLEDGEMENTS The principal author of this edition was Dr Richard Robinson, now an ind ependent consultant, with contributions from Simon Done, Dr Greg Morosiuk and Dr John Rolt of TRL Limited. The example of field survey procedures described in Appendix B is based on one develope d by High-Point Rendel. OVERSEAS ROAD NOTES Overseas Road Notes are prepared principally for road and transport orga nisations in developing countries. A limited number of copies are available to other organisatio ns and to individuals with an interest in road management, and may be obtained from: Centre for International Development TRL Limited Crowthorne Berkshire, RG45 6AU United Kingdom www.trl.co.uk Limited extracts from the text may be reproduced provided the source is acknowledged. For more extensive reproduction, please contact TRL using the postal or website a ddress above. v Foreword A good road network is vital for the development of any country, and par ticularly so for most developing countries. Rural areas are the home for large numbers of peop le, the farms which produce crops for consumption and export, and strategic sites such as power stat ions and border posts. However, rural roads, along with other rural facilities, often receive less than their fair share of spending and many fall into disrepair. Communities become isolated and lose their access t o schools, health centres, social support networks and sources of income. At the same time, teachers and m edical staff are unable to visit the rural facilities where they do their work. Crops cannot be transport ed to markets and much needed income is lost. Rural poverty grows and livelihoods become unsustainable . To reverse this trend, rural roads must be well managed, money must be s pent efficiently and the needs of the road users – farmers, villagers, traders and government offici als – must be met. This is good road management and, if carried out in tandem with other institutional improv ements, should bring about sustainable improvements in the livelihoods of the rural population. Thi s document is aimed at providing suitable guidance for road managers so that they can manage th eir rural road networks more effectively. In many rural areas roads fall into two groups. The first carry very low volumes of motorised traffic, but social use is vital and significant. The second group carry higher volum es of traffic and economic use is dominant. This document is applicable to both groups but is intended pri marily for the second group. Additional considerations are needed for very low volume roads and these are dealt with more fully in Overseas Road Note 20. Martin Sergeant Head of Profession Infrastructure and Urban Development DFID vi vii CONTENTS Page 1 Introduction 1 Purpose and scope 1 Structure of the Note 2 2 Road network management 3 Aims 3 Activities 3 Management cycle 6 3 The role of the maintenance engineer 8 4 Network information 10 Information needs 10 Classification 10 Network definition 10 Item inventory 12 Content and preparation 12 Recording 13 Updating 13 Presentation 13 Traffic 16 5 Assessing needs 17 Defects 17 Safety inspections 18 Network screening surveys 19 Visual inspections 19 6 Determining options 21 Basis of approach 21 Scheduled treatments 21 Condition-responsive treatment selection for unpaved roads 25 Condition-responsive treatment selection for paved roads 26 Diagnosing the cause of deterioration 26 Specifying the work required 33 7 Choosing actions 34 Selection from among options 34 Resource estimation 34 Choice of work method 34 Choice of technology 34 Procurement by contract 36 In-house works 37 Estimating 38 viii Page Costing 38 Works packaging 43 Priority assessment 44 Purpose 44 Example method 44 Alternative prioritisation methods 46 Determining the work programme 47 8 Preparation and operations management 49 Works design 49 Procurement by contract 49 Forms of contract 49 Specifications 50 Contract procedures 51 Operations management of in-house works 52 9 Monitoring and audit 57 10 Information systems 59 References 60 Appendix A: Glossary 62 Appendix B: Field survey procedures 67 Appendix C: Traffic counts 82 Appendix D: Standard forms 85 Appendix E: Illustrations of defects 92 1 TRL Overseas Road Note 1, 3rd edition 1 Introduction Purpose and scope 1 . 1 This Note is a practical guide to the management of road maintenance. It provides a rational approach to help maintenance engineers organise and control the activiti es for which they are responsible. The aim is to improve effectiveness and efficiency, and mak e more productive use of maintenance resources. The Note is targeted primarily at those district engineers in developing and emerging countries who do not have access to computer-based information and management systems. However, although a paper-based system of management is describ ed, this could easily be computerised using simple spreadsheets, if required. Parts of the Note m ay also be used in conjunction with existing computer-based systems. 1 . 2 The Note covers the management of ‘maintenance’ and ‘renewal’ activities, but does not cover ‘development’ (new construction, widening, new carriageway works), or ‘rehabilitation’ to restore deteriorated roads to a maintainable condition. Winter maintenan ce is not included. It covers ‘programming’, ‘preparation’ (treatment design and works pr ocurement) and ‘operations management’. It does not cover ‘strategic planning’. The Note c an be applied to the management of single-carriageway asphalt-surfaced and portland cement concrete road s carrying up to about 5,000 vehicles per day. It can also be applied to gravel and earth roads . It covers carriageway and off-carriageway features of roads in rural areas. The Note can also be a pplied in urban areas, but some particular problems of urban roads (street lighting, urban drainag e, permits for utility openings, traffic management, etc.) are not covered. Advice on bridge i nspection is given separately in Overseas Road Note 7 (TRRL 1988) and on traffic safety management in Towards safer roads in developing countries (TRRL 1991) and Highway safety guidelines (IHT 1990). 1 . 3 Management of road network maintenance and renewal can be considered to have the following objectives:  Network safety: – complying with statutory obligations to provide minimum safety standards . – meeting users’ needs by reducing safety risks to an acceptable level.  Network serviceability:– ensuring availability so that roads or traffic lanes are not closed for unacceptably long periods. – achieving integrity by applying consistent standards along routes, inclu ding consistent signing. – maintaining reliability by providing a ‘level of service’ that mee ts users’ needs for mobility. – enhancing quality of all aspects of the driving environment.  Network sustainability: – minimising cost over time to both road users and the road administration . – maximising value to the community and minimising environmental damage. – maximising environmental contribution. 1 . 4 The Note offers advice on techniques basic to good management practice, but does not set out to define ‘model’ systems that should be copied generally. It does not describe all the management procedures an ideal road administration should follow. This i s because, in any location, the best management system will be one that is matched closely to the technical skills, human resources and equipment available, and the most effective procedur es will be those that are appropriate to the experience and capabilities of its staff. Using this Note, engineers will be able to assess the range of management techniques applicable to road maintenance and renewal, and so identify methods that can usefully be put into practice within the context of their own organisations. 2TRL Overseas Road Note 1, 3rd edition Structure of the Note 1 . 5 Following this introduction, Chapter 2 sets out the key management activ ities to be undertaken and Chapter 3 summarises the responsibilities of the maintena nce engineer. Chapter 4 describes basic information about the road network that is needed to und erpin these activities. The management activities are described in more details in Chapters 5 to 9, which explain each stage of the process in turn. Chapter 10 discusses the use of computer-based road information and management systems. A glossary of terms is included as Appendix A. Other appendices provide additional details of some of the technical procedures and give examples of standard forms. A final appendix illustrates typical defects found on roads. 3 TRL Overseas Road Note 1, 3rd edition 2 Road network management Aims 2 . 1 Road network management is a process that attempts to optimise the overa ll performance of the road network over time. The process comprises a number of ‘activi ties’ (or measures) that will have ‘impacts’ (or effects) on the road network. Impacts include those on the following:  Level of service or road conditions.  National development and socio-economic issues.  Road user costs.  Accident levels and costs.  Environmental degradation.  Road administration costs. 2 . 2 The way in which road maintenance and renewal address these impacts shou ld be set out in a ‘road maintenance policy’. This should be part of the road adminis tration’s ‘roads policy’, which defines aims, objectives and performance indicators for the organisation as a whole. The road maintenance policy should define aims and set objectives in each of the above six impact areas. Objectives should be specific, measurable, achievable, relevant and time -bound, and should reflect the relative importance of each of the areas of impact. In the absence o f a pre-defined organisational policy, the engineer should take the initiative to formul ate an appropriate road maintenance policy. Guidance on this is included in Road maintenance management: concepts and systems (Robinson and others 1998). 2 . 3 A key aspect of policy formulation is involvement in this of road users, as ‘customers’ of the road administration. Road users will often have a different perspective on the importance of different impacts than will officials of the road administration or elec ted members, and it is important to reflect this in the roads and road maintenance policy. In s ome countries, existence of a ‘roads board’ provides an easy opportunity for such user consultat ion. However, the ‘political’ dimension is also important, and elected members should also be involved in the policy formulation process. 2 . 4 The objectives included in the road maintenance policy provide the basis for deriving ‘standards’ and ‘intervention levels’ that can be used to pr ovide the detailed operational criteria for determining maintenance treatments (see Section 6). Activities 2 . 5 Activities on pavements and shoulders can be defined under the headings of ‘operations’, ‘maintenance’, ‘renewal’, ‘development’ and ‘dispos al’, as in Table 2.1. ‘Operations’ are ‘management’ activities; ‘maintenance’, ‘renewal’ and ‘development’ are ‘works’ activities. Similar groupings of activities can be defined for other features, such as bridg es and structures, footways and cycle tracks, street lighting, road signs and furniture. 2 . 6 Activities can be broken down into ‘tasks’ for the purposes of ope rational costing and management. For example, surface dressing might be broken down into the tasks of: i Place signs and traffic control devices. ii Prepare existing surface and carry out any pre-patching. iii Ensure surface is clean and free from loose material by brushing. iv Mask surface iron-work. 4TRL Overseas Road Note 1, 3rd edition Table 2.1 Activities related to road pavements and shoulders Group Cat egoryType Examples of activities Operations. Network management. Strategic planning. Programming. Preparation (design and procurement). Operations management. Administration. Finance and accounts. Personnel management. Facilities management. Toll collection. Maintenance of depots. Policing. Speed enforcement. Axle load control. Maintenance. Routine planned.Cyclic. Grass cutting. Cleaning side drains. Routine unplanned. Reactive. Patching. Crack sealing. Winter. Salting/gritting. Snow removal. Emergency. Traffic accident removal. Landslip removal. Periodic (planned). Preventive. Fog seal. Slurry seal. Resurfacing. Single surface dressing. Thin overlay. Road marking. Renew road markings. Renewal. Overlay. Structural asphalt overlay. Bonded concrete overlay. Pavement reconstruction. Mill and replace. Inlay. Development. Widening. Lane addition. Shoulder provision. Realignment. Local geometric improvement. Junction improvement. New section. Dualling. By-pass construction. Disposal. Asset disposal is seldom used in connection with pavements and shoulders except in a few cases of ‘de-gazetting’ of a road. 5 TRL Overseas Road Note 1, 3rd edition v Apply bituminous binder. vi Apply chippings. vii Roll. viii Re-expose iron-work by removal of masking. ix Apply lines and markings. x Remove signs and traffic control devices. 2 . 7 The term ‘rehabilitation’ is sometimes used to refer to the works necessary to restore a road that has not been maintained back to a ‘maintainable’ condition. T his differs from ‘renewal’ which is an expected activity that should be planned for as part of a normal a sset management regime. Rehabilitation normally requires pavement overlay or reconstruction, plu s reconstruction of drainage and other road-side features. Often, the opportunity is taken t o carry out some ‘development’ activities at the same time as rehabilitation. 2 . 8 Network management activities (sometimes referred to as ‘management functions’) can be described in more detail under the following four headings:  Strategic planning – long-term decisions affecting the whole of the road network, under taken primarily for the benefit of senior managers and policy-makers (not cov ered by this Note).  Programming – determining those parts of the road network where work can be under taken with available resources in the next budget period.  Preparation – design of works for individual sections of road, issuing of contrac ts or works orders for works for which there is a budget commitment.  Operations management – managing and supervising on-going works on individual sub- sections of road. 2 . 9 For funding purposes, works are normally assigned to ‘budget heads’ . These are often termed ‘capital’ and ‘recurrent’ although, in some countries, other budget heads are also used. Both maintenance and renewal works should be funded from the recurrent budget . However, often, periodic maintenance and renewal works are assigned to the capital budge t. This reduces the flexibility to optimise management of the network over the life cycle of the roads. However, maintenance engineers must work within whatever budgeting procedures are in place in their organisation. 2 . 1 0 In many countries, ‘budgeting’ is carried out on an annual cycle. Budgeting is part of the ‘programming’ activity. Initially, this is used to produce a progr amme of required works under each budget head, listed in priority order (see Section 7). This progr amme is submitted for approval to the budget authority (often the Ministry of Finance). An approved p rogramme is then authorised, and a budget awarded for its implementation. The maintenance engineer ca n then produce a list of committed works, which can be prepared for execution. Budgeting procedur es differ from country-to-country and from organisation-to-organisation. They are not d iscussed further here. 2 . 1 1 The programme of committed works is implemented throughout the year. The maintenance engineer arranges how best to do this, in terms of both method of procur ement and timing. Determining the best timing for works is known as ‘scheduling’. Pr ocurement and scheduling are discussed in Section 8. 2 . 1 2 This Note is concerned with the network management activities of program ming, preparation and operations management, related to the works of maintenance and renew al for the features of pavements, shoulders, drainage and road furniture. 6TRL Overseas Road Note 1, 3rd edition Management cycle 2 . 1 3 All maintenance management activities can be carried out by using the fo llowing steps, which are known as the ‘management cycle’: i Define aims (what is the required objective of the activity?). ii Assess needs (how does the current situation fall short of the required aim?). iii Determine options (what alternative approaches can be used to address t he identified need?). iv Choose actions (which option should be adopted?). v Implement (carry out the activity to meet the aim). vi Monitor and audit. – review how well the outcome of the implementation actually meets the aim – to providefeed-back on how the setting of aims can be improved in the future. – review to see if the implementation procedures can be improved. – ensure that the implementation has been undertaken in the correct techni cal manner and that money has been spent properly. 2 . 1 4 Table 2.2 shows the management cycle steps for the network management ac tivities of programming, preparation and operations management, and indicates where aspects are described in more detail in this Note. 7 TRL Overseas Road Note 1, 3rd edition Table 2.2 Management cycle for programming, preparation and operations m anagement Network management activity Steps in the Preparation (see Section 8) management Operations management cycle Programming Design Procurement (see Section 8) 1 Define aims. Determine work programme that can be Design of works. Issue of contract or work Undertake works activity. carried out with next year’s budget. i nstruction. 2 Assess needs. Measure road conditions for Detailed surveys and Confirm work type to be Determine the extent and quantity of renewal, periodic and routine investigations to assess road undertaken.work from: detailed inspections for reactive works (see Table 2.1) conditions. renewal, periodic and routine reactive (see Section 5). works; from the maintenance standard for routine cyclic works. 3 Determine options. For renewal, periodic and routine reactive Compare road conditions with Identify options for carrying out Dete rmine detailed options for works, compare road conditions with design standards for renewal work by contract or with in-house undertaking the remedial works. maintenance standards to determine and periodic works (other works resources, with equipment or treatment options; for routine cyclic not normally designed) to labour-based methods, and for works, apply standards to determine determine design options. different specifications. treatment frequencies (see Section 6). 4 Choose actions. Choose the most appropriate treatments Cost rates applied to design Select the most appropriate Choose the most a ppropriate action from from the options available to address options to determine which options from the above using the available options and then apply a needs; this will require consideration of design is most appropriate. pre-agreed criteria. ‘performance standard’ to determine costs and priorities to produce a work performance targets, and labour, programme within the budget equipment and material resource (see Section 7). requirements. 5 Implement. Submit works programme for Undertake design, produce Prepare and let contracts or issue Undertake and supervise work. approval. drawings, etc. work instructions. 6 Monitor and audit Review programme produced Review or check design. Review contract or work Review achievement against target. (see Section 9). prior to start of next Review design procedures. instruction. Review procedures for managing works programming cycle. Review procurement activities. Review programming procedures. procedures. Length of cycle. Typically one year. Typically less than one year.Typically days or weeks. 8TRL Overseas Road Note 1, 3rd edition 3 The role of the maintenance engineer 3 . 1 Roads are expensive to build. They repay their initial investment only b y means of long-term care and maintenance. A road system that is well maintained brings impor tant social and economic benefits:  Roads have a longer lifetime of service because their surfaces do not de teriorate so rapidly.  The transport links on which the economy and development depend are kept in good working order.  Vehicle operating costs are reduced because traffic is able to run smoot hly.  Transport operations are safer and more reliable.  Pollution and noise are reduced.  Long-term network maintenance and renewal costs are reduced. The maintenance engineer responsible for operations at regional or distr ict level has a key role to play in achieving these benefits. Success depends largely on the way the task of management is approached. 3 . 2 In simple terms, maintenance management aims to get the right resources (people, materials and equipment), to the right place on the road network, to carry out the right maintenance or renewal work, at the right time. This task involves five main areas of responsibility:  Assessing the need for works on the network (Chapter 5).  Identifying maintenance and renewal treatments that can address needs ( Chapter 6).  Preparing the annual programme of works, arranging that funds are alloca ted fairly to the various parts of the road network, and deciding on priorities if the fun ds available do not allow the full programme to be undertaken (Chapter 7).  Authorising and scheduling work, and making arrangements for it to be ca rried out effectively and efficiently (Chapter 8).  Monitoring the quality and effectiveness of maintenance activities (Cha pter 9). These responsibilities underpin the sequence of maintenance management d escribed in the relevant sections of this Note. 3 . 3 In performing the management role, maintenance engineers will, of course , have many hours of office work on network management and administrative matters. But it is essential that field visits are made as often as possible. Seeing things for themselves on si te help to overcome many of the problems that can affect maintenance and renewal operations. There a re several reasons why site visits are important:  They enable the maintenance engineer to become thoroughly familiar with road conditions in the area, and so recognise trouble spots and other places where difficul ties are likely to occur.  First-hand knowledge can be gained of the extent and quality of the main tenance that has actually been carried out, instead of having to rely on reports from oth ers.  This knowledge can be used to assess maintenance priorities with much mo re confidence.  Presence of the maintenance engineer on the spot means that advice can b e given on problems as they arise. 9 TRL Overseas Road Note 1, 3rd edition  Seeing the maintenance engineer regularly on site boosts the morale of r oad gangs and so improves their standard of work and output; site visits are the most eff ective way of demonstrating commitment of the maintenance engineer to getting the job done successfully. 3 . 4 Maintenance engineers need detailed knowledge of all maintenance activit ies, but should delegate work to more junior engineers, technicians and foremen wherever possible. The time and skills of the maintenance engineer are best utilised by concentrating on programming (including budgeting) and the monitoring of maintenance operations. Procurement ca n be undertaken by either engineering or administrative staff. Design can be carried out by junior engineers or by consultants working under contract. The supervision of the majority of m aintenance works (‘operations management’) should be delegated to a foreman or te chnician. The maintenance engineer’s knowledge of road conditions provides the basis of decisio ns on which operations need personal supervision and which operations can be safely delegated to oth er staff. Only where there are problems requiring complicated treatment and on-the-spot judgement s hould the maintenance engineer become personally involved in managing site operations. The key point is to avoid the maintenance engineer’s time being taken up by simple operations that less qualified staff are able to manage. 3 . 5 Delegation will only succeed if staff have the knowledge and competence to fulfil the duties they are given. Although outside the scope of this document, training is an important part of the responsibilities of the maintenance engineer. Important points to consid er are:  All members of staff should have appropriate training.  Training should be built into the work programme and include practical o n-the-job experience as well as more formal courses.  Training should be an on-going feature of employment in the maintenance organisation, so that competent staff are available to take over when more experienced personn el are promoted, transferred to other duties, or leave. For more details on training see Road engineering for development (Robi nson and Thagesen 2004). 3 . 6 Effective maintenance management requires appropriate information to sup port management decisions, and the quantitative basis for this is provided through data. The processing of data is facilitated by the use of computer-based systems, and these are increasi ngly being used in all countries for maintenance management. A growing range of specialised sof tware is available to help process data and analyse problems. The application of computers to maintenance management is a subject where staff training may be particularly useful. Computers can save time, as well as freeing the maintenance engineer for inspection and monitoring on site. But expenditure on computers can prove an expensive mistake if the system is not chosen wit h care and if suitable personnel are not available to make the best use of it. Maintenance can be managed efficiently without a computer, and Chapter 10 of this Note provides some guidance o n how this can be done. 3 . 7 For most organisations, the management approach recommended in this Note will take some time to implement – perhaps a period of several years. The maintenanc e engineer should not try to put everything into practice at once. It is better to introduce new meth ods and procedures gradually, starting with straightforward measures that will produce earl y and positive results. Proceed step-by-step, and wait until one stage is working reasonably wel l before moving to the next. Concentrate first on the sections of road that carry the largest v olumes of traffic and ensure these are adequately maintained before dealing with less busy roads. 10TRL Overseas Road Note 1, 3rd edition 4 Network information Information needs 4 . 1 Each step in the management cycle requires access to information to enab le the step to be undertaken. Information is central to the road maintenance management. B asic information about the length and characteristics of the roads to be managed is obviously e ssential. However, in addition, information is needed about the ‘importance’ of individu al roads and the traffic levels on them. Roads are normally classified according to their ‘importance’ . Classification 4 . 2 Classification is the process by which roads are grouped into a hierarch y of classes, or systems, according to the character of service they are intended to prov ide. Basic to this process is the recognition that individual roads do not serve travel independently, but that most travel involves movement through an inter-connected network of roads. Road clas sification aids the channelisation of travel within the network in a logical and efficient m anner. Roads within each class are expected broadly to provide a similar level of service. Thus, roads of each class are subject to common objectives, standards and intervention levels (see Ch apter 6), and these may differ for roads of different classes. The road classification should th erefore be designated as part of the policy framework. It is appropriate for the maintenance engineer to adopt a suitable road classification for maintenance purposes, if one does not already exist. 4 . 3 Table 4.1 gives examples of how road networks can be broken down into di fferent classes, depending on the nature of the classification. Thus, a network classifie d ‘functionally’ could have the following components:  Arterial roads – the main routes connecting national and international centres, wit h relatively high levels of traffic, speeds and average trip length.  Collector roads – roads linking rural areas to adjacent urban centres or to the arte rial network, with traffic flows and trip lengths of an intermediate level.  Access roads – the lowest level of road in the network, with low vehicle flows an d short trip lengths, and with substantial proportions of total movements likely to b e by non-motorised traffic and pedestrians. Network definition 4 . 4 Classification and standards relate to the geographic location of the di fferent parts of the road network. Thus, a system of ‘network referencing’ is needed for roa d maintenance management. The network is usually broken down into a series of ‘links’ or ‘ sections’. ‘Links’ are lengths of road where traffic volume is reasonably uniform; ‘sections’ are lengths of road that are uniform in terms of their physical characteristics. Sections are normally the basic unit of a road network used for management purposes, but these are often sub-divided into ‘sub-sectio ns’ for detailed analysis of road condition. The start and end of road sections are sometimes called ‘nodes’. The maintenance engineer should reference the network. Sections should be selected to ha ve homogeneous characteristics, with the following being typically uniform for a sectio n:  Road class.  Traffic level (i.e. sections should not include any major junctions).  Road geometry.  Pavement construction type.  Other administrative data considered appropriate, such as administrative boundaries, speed limits, etc. 11 TRL Overseas Road Note 1, 3rd edition 4 . 5 The maintenance engineer should produce a roads register, or ‘gazette er’, consisting of a list of links or sections to define the road network. Each section should be given a unique label for identification purposes. The format of this label can reflect the class of road. An example extract from a roads register is shown in Box 4.1. 4 . 6 It is convenient if the start and finish of sections are identified phys ically on the road. Road-side marker posts can be used for this, and it is often convenient to place a dditional marker posts at kilometre intervals. Marker posts need to be constructed in a robust man ner to ensure their permanence and to reduce the possibility of their being damaged or moved inadvertently. It is particularly helpful to inspection teams if marker posts display the sec tion label. 4 . 7 Referencing a network is a surprisingly time-consuming activity if it is done in a systematic and unambiguous way. But good referencing is crucial, since it provides the locational basis for all subsequent road management activities. Table 4.1 Examples of different road classifications Nature of classification Classes Network priority PrimarySecondary Tertiary Functional Arterial or trunk Collector or distributor Access Type Major (road has mainly an Minor (road has mainly economic function) a social function) Major rural or non-urban U rban Rural transport infrastructure Designation (ownership) National Provincial/ MunicipalLocal (rural) Community regional (urban)government (undesignated) Typical characteristics Physical characteristics Two and Two lanes Single lane Tracks, trails more lanes paved or gravel gravel or and paths paved earth Traffic (vehicles/day) >2000 50-2000 <50 <10 Journey function Mobility Access Trip length Long Short Percent of total ~20 ~10 ~30 ~40 network length 12TRL Overseas Road Note 1, 3rd edition Item inventory Content and preparation 4 . 8 The ‘item inventory’ is a set of information about the basic engin eering characteristics of the road network. It defines the key features of each section of road. This information is an essential reference source for inspection and analysis. The content of the invento ry should be directly relevant to maintenance management. When it is first drawn up, it should be as simple as possible and need contain information on the following items, for carriageway and shoulders only:  Section length.  Type of surface and construction.  Cross-section width. 4 . 9 As the inventory is built up, further information can be added on all fa ctors influencing the management activities needed to prepare the work programme (see Chapter 7). In addition, data about the distribution and engineering properties of soils will be usefu l in identifying possible sources of maintenance materials. The level of detail recorded in the in ventory may depend on the road class. Inventory data is expensive to collect and keep up-to-date. Generally, the inventory should be as simple as possible and not be overloaded with unnecessary i nformation. Information should only be collected when there is a clearly-defined need, the cost of which outweighs the cost of collection. Ultimately, a typical inventory could contain the followi ng information: Box 4.1 Example of a roads register Leagrave District DATE: November 1, 2003 Node Section Length label (m) S tart EndDescription B486/20 603 563424 572392 Bramingham Road from Derby Rd to Weltmore Road B486/30 1,750 572392 572341Bramingham Road from Weltmore Rd to Park Road B488/10 1,023 514381 539409Leagrave Road from 50km/h limit to Weltmore Road B488/20 491 539409 546424 Leagrave Road from Weltmore Rd to district boundary 2U164/10 960 525394 535406Parkman Crescent from liquor store to bakers 2U210/10 823 534353 522369May Avenue from Merryn Road to West Street 2U245/10 1,166 539409 572392Weltmore Road from Leagrave Rd to Bramingham Road 2U257/10 437 564420 569409 Matthews Road from Bramingham Road 2U258/10 197 573404 566402Hannah Road from Bramingham Road 2U259/10 2,264 571362 532340Merryn Road from Bramingham Road 2U355/10 703 539360 554340Margaret Road from Merryn Rd to Telford Road 2U1401/10 415 553399 546387Bosmore Road from Weltmore Rd to Carisbrooke Road 2U1401/20 813 548384 527376Carisbrooke Road from school to Limbury Path 2U1401/30 419 545389 536375Icknield Road from Carisbrooke Road 2U1503/10 339 563365 551361Larkhall Road from Merryn Road 2U1504/10 335 551348 562353Kenilworth Road from Margaret Road 2U2101/10 266 527354 532363Ludlow Road from May Avenue 2U2102/10 234 522357 515350Balcombe Road from May Avenue 2U2103/10 246 518372 525366 West Street from health clinic to Limbury Path 13 TRL Overseas Road Note 1, 3rd edition  Sections: the length of each section in the network.  Cross-section: the width of the carriageway and shoulders, with informat ion on whether kerbs, footways or side drains are present.  Pavement: the type, thickness and, if possible, the age of the pavement on the carriageway and on the shoulders.  Alignment: the chainage of characteristic points in the alignment, such as the location of crossroads, culverts, bridges, and sharp curves; details of steep gradie nts and the radii of sharp curves may also be recorded.  Structures: the type and dimensions of major bridges, culverts and retai ning walls.  Furniture: information on road signs, guard rails, lighting and other fe atures.  Soils: information about the soil type along the road (clay, sand, rock , etc.), and location of identified deposits of road materials.  Rainfall, topography and runoff.  Land use: such as town, village, woods, farmland. Recording 4 . 1 0 Appendix B of this Note describes the field procedures used in setting u p an inventory, including the organisation of teams and transport. The maintenance engin eer can delegate the preparation and day-to-day supervision of the work to a senior technicia n who understands fully the procedures. 4 . 1 1 Inventory data may often be collected by driving slowly along the road a nd stopping for measurement of characteristic cross-sections. Chainages can be recorded on the car’s trip-meter. Information on pavement and structures can be obtained by inspection. Ho wever, some testing may be necessary, depending on the application to which the inventory will b e put. Horizontal curvature can be determined with a compass, or in relation to the turning angle of the car’s steering wheel. Gradients can be measured by means of a simple fall meter. Updating 4 . 1 2 Although the preparation of the inventory is a once-only activity, it is very important that it is kept up-to-date. Information on changes to the network, such as new surf acings and reconstruction works, need to be entered into the item inventory, otherwise its usefuln ess is reduced. Assessing maintenance needs is then made more difficult. Presentation 4 . 1 3 There are a number of ways of presenting the information recorded in the inventory:  List.  Schematic maps.  Strip maps.  Card index systems. 4 . 1 4 Where computers are available, it is simple to store the inventory as a list in a spreadsheet or simple database. This approach simplifies subsequent data additions, upd ates, analysis and reporting on the information contained. 14TRL Overseas Road Note 1, 3rd edition 4 . 1 5 Figure 4.1 shows a typical schematic map. It is basically a road plan of the area marked to indicate traffic levels, categories of road surface and road widths. Thi s kind of map is particularly helpful in giving an overview of the whole network, enabling the mainten ance engineer to see at a glance how roads with differing features relate to each other. Figure 4.1 Example of a schematic map of a maintenance district CategoryAnnual average daily traffic Surface type Width m. 2 3 4 5 6 7 8 7.0 7.0 5.0 – 7.0 7.0 5.0 5.0 3.5 1000+ 500 – 1000 200 – 500 > 200 < 200 50 – 200 up to 50 Bituminous Bituminous Bituminous Gravel Bituminous GravelEarth 0 10203040 50km Scale INVENTORY Major Bridge (Reference No.) Sub-standard Alignment Principal Towns K DE F 66/4 YX G M U C RZ QS T V 38/4 W N District Boundary B A 12/1 15/3 23/2 P J H KEY 15 TRL Overseas Road Note 1, 3rd edition 4 . 1 6 Figure 4.2 is an example of a strip map. This is a simple annotated draw ing which records significant information about a section of road and its surroundings. It s principal use is in the field, where it provides a quick means of reference during inspections and surv eys – especially for the location of chainage. It is often convenient to staple strip maps togeth er to form a pocket-sized notebook for each road. 4 . 1 7 Card index systems are useful for registering details of items such as r oad structures and road signs. They can easily be updated when these items are repaired or repla ced to provide a continuous record of their condition and maintenance history. A12 102/1 Gravel (5km) Gravel (2km) 100 100 80 Clayey Sands Clayey Sands To Y To Quarr y 7km To X B River G Swamp 91/1 89/1 River M Gravel 78/1 B234 A A B121 To Z 12 Figure 4.2 Example of strip map showing road inventory 16TRL Overseas Road Note 1, 3rd edition Traffic 4 . 1 8 The need for some maintenance activities will depend on the traffic volu me and the distribution of axle loads on sections of the road network. Traffic volu mes can be used to classify roads into broad categories for maintenance management purposes. A high level of accuracy is not required. 4 . 1 9 On roads carrying more than about 1000 vehicles per day, a one-day manua l count will usually be sufficient to provide an estimate of the ‘annual average d aily traffic’ (AADT) for the maintenance classification. Counts should be made every few years at sel ected counting stations. Traffic in intervening periods and future traffic can be estimated using growth factors. On roads with light traffic, it is normally sufficient to make a rough estimate of tra ffic using ‘moving observer counts’. These involve measuring traffic whilst driving along the roa d. The maintenance engineer should habitually carry out moving observer counts when driving on all r oads to provide regular checks on traffic levels. Methods of traffic counting and analysis are d escribed in Appendix C. 4 . 2 0 The distribution of axle loads is needed to design some pavement renewal works. Measurements are normally made using portable weighing scales, as descri bed in Overseas Road Note 40 (TRL 2003). Measurements are normally made only in association with s pecific planned works. If the traffic volume is low, all passing vans, trucks and buses are weighed on an ordinary weekday. If the traffic volume is large, then a sample is normally taken . For example, every third passing commercial vehicle is stopped and weighed. 4 . 2 1 When the maintenance system is first applied, it will probably not be po ssible to include traffic counts as part of the maintenance planning process. Initially, t raffic levels on the roads within the maintenance district may have to be estimated. But there is n o substitute for counting vehicles. As the maintenance system develops, the traffic counting metho ds described in this Note should be introduced gradually into the management process. 17 TRL Overseas Road Note 1, 3rd edition 5 Assessing needs Defects 5 . 1 Information is needed about where the network is defective to assess mai ntenance needs. The comparison between measured road condition and pre-defined standards, or intervention levels (see Chapter 6), provides a basic statement of shortfall in serviceability, which can be translated into maintenance need. It is convenient to characterise defects under the fol lowing headings:  Paved roads: – roughness (unevenness); – surface distress (rutting, cracking, ravelling, pot-holes, etc.); – structural adequacy; – pavement texture and friction.  Unpaved roads:– roughness, including corrugations; – surface distress (loss of camber, rutting, pot-holes, ravelling or loos e material); – gravel loss; – dust. 5 . 2 Defects can be assessed using manual or mechanised methods. Visual inspe ctions are normally used to record conspicuous defects of pavement, shoulders, side drains, culverts and road furniture. Mechanised data are more repeatable, reproducible and, genera lly, can be collected more efficiently. Their use is normally limited to the assessment of the need for pavement renewal works. Reference should be made to Overseas Road Note 18 (TRL 1999) for descriptions of the following mechanised defect assessment methods for use in this context:  Roughness.  Structural adequacy: – deflection beam; – falling weight deflectometer (FWD).  Pavement texture and friction:– sand patch test; – portable skid-resistance tester. Mechanised methods of assessment are not discussed further in this Note, which concentrates on visual assessment of:  Paved roads: – surface distress.  Unpaved roads:– surface distress; – gravel loss. 5 . 3 Some defects deteriorate relatively rapidly, so it is not practical to a ssess the treatment needs for these on the basis of inspections. Examples are the roughness of gra vel roads, ditch siltation, vegetation growth, etc. ‘Scheduled’ maintenance treatments are use d to treat defects of this nature, and treatments can be carried out several time a year. This is discussed in Chapter 6. Scheduled treatments are also used for all routine cyclic works (see Table 2.1). 18TRL Overseas Road Note 1, 3rd edition Safety inspections 5 . 4 Safety inspections should be designed to identify all defects likely to create a danger or serious inconvenience to users of the network or the wider community. Su ch defects should include those of a serious nature at critical locations requiring urgent attenti on, and those where the nature and location are such that longer response times are more appropriate. T he aim is to provide a practical and reasonable approach to managing the risks associated with road maintenance management. The inspection regime should take account of risk to all roa d users and, in particular, to pedestrians and non-motorised traffic, who are the most vulnerable. 5 . 5 Safety inspections are normally undertaken from a slow-moving vehicle at frequencies that reflect the characteristics of the particular road and its use. In heavi ly-used urban environments, particularly when inspecting footways, it may be necessary to walk these surveys. Additional inspections may be necessary in response to user or community concern, a s a result of extreme weather conditions, or as a result of monitoring information (see Chapt er 9). 5 . 6 Frequencies of safety inspections should be based upon consideration of:  Road class.  Traffic use, characteristics and trends.  Incident and inspection history.  Characteristics of adjoining network.  Wider policy or operational considerations. The frequencies shown in Table 5.1 can be taken as a starting point. Table 5.1 Safety inspection frequencies Feature Class Frequency Pavements and shoulders. Arterial.Monthly. Collector. 3-monthly. Access. 12-monthly. Footways. Busy urban area. Monthly. Other. 12-monthly. 5 . 7 During safety inspections, all observed defects that provide any degree of risk to users should be recorded, irrespective of the likely level of response. On-site judge ment will always be needed to take account of particular circumstances. For example, the degree of risk from a pot-hole depends not just on its depth, but also on its surface area, its locatio n and the traffic level using the road. Two categories of safety defect can be considered:  Category 1 – those that require prompt attention because they represe nt an immediate or imminent hazard, or because there is a risk of short-term structural det erioration; examples are: – traffic accidents; – broken-down vehicles in the carriageway; – carriageway, shoulder or culvert wash-out; – collapsed culvert; – debris on the carriageway, etc.  Category 2 – all other defects. 19 TRL Overseas Road Note 1, 3rd edition 5 . 8 Category 1 defects should be corrected or made safe at the time of the i nspection, if reasonably practicable. In this context, ‘making safe’ may constit ute displaying warning signs, coning-off, or fencing-off to protect road users or the public from the defect. If it is not possible to correct or make safe at the time of the inspection, which will generally be the case, repairs of a permanent or temporary nature should be carried out as soon as possible and, in any case, within 24 hours. The aim should be to carry out permanent repairs within one mo nth. Where temporary signing or works are used, arrangements should be made for a special ins pection regime to ensure the integrity of the signing or repair until a permanent repair can be m ade. 5 . 9 Category 2 defects should be repaired within planned work schedules, wit h priority depending on the degree of defectiveness, traffic and site characteristi cs. These priorities should be considered when compiling the work schedule, together with access requir ements, other works on the network, traffic levels and the need to minimise traffic disruption. Network screening surveys 5 . 1 0 In assessing the condition of the road, it is advisable to adopt a two-s tage process of inspection:  Network screening survey – in the first stage, an engineer or senior technician undertakes a drive-over survey of the network to identify those sections likely to ne ed treatment.  Visual inspection – the second stage involves a small team, led by a technician, whose task is to determine the requirements for reactive and periodic works, and to ident ify those sections where detailed investigations are needed prior to carrying out renewal works. The advantages of this approach are that it provides a double-check on t he state of the road network and the scale of maintenance requirements. It uses resources in a cost-effective way by directing them specifically to locations that call for skilled inspectio n and treatment. 5 . 1 1 The main purpose of the network screening survey is to identify the need for the more detailed visual inspections. For example, the survey can be used to screen-out th ose sections that are up-to- standard, enabling the visual inspections to concentrate on those sectio ns that are likely to need treatment. The survey applies a serviceability ‘rating’ to pavemen ts, shoulders, footways and side drains on a scale of ‘5’ (good) to ‘1’ poor. The survey an d rating methods are described in Appendix B. The methods also record the likely remedial treatments that are neede d for each section. 5 . 1 2 The results of the survey can be used to rank individual sections in ter ms of defectiveness. The maintenance engineer needs to review this to determine which section s are worth further investigation through a visual inspection. Clearly, road pavements ranke d as ‘5’ (good) would not normally be investigated further, whereas those ranked as ‘1’ or ‘ 2’ would almost certainly be included in a visual inspection programme. The further inspection of roa ds ranked ‘3’ or ‘4’ would depend on the likelihood that they will need periodic or renewal treatme nts. The notes on likely treatment options recorded on the survey form will give guidance on this . The actual survey schedule produced will also depend heavily on the survey resources and t ime-scale available to the maintenance engineer for visual inspections. 5 . 1 3 It is possible to compare average ratings for the whole network year-on- year to see if overall conditions are improving, deteriorating or staying constant. Although th is can provide useful information, the subjective nature of the surveys means that there could be significant errors attached to the results. Network screening surveys can be undertaken in conjunction with safety inspections – discussed earlier. This maximises the use of survey res ources. Visual inspections 5 . 1 4 The maintenance engineer should aim to have the targeted parts of the ro ad network inspected at least once a year, and should try to improve this frequency if at all practicable. The most appropriate time of the year for this will depend on the climatic c onditions. The drainage system should ideally be inspected in wet conditions, since this can onl y be evaluated satisfactorily when there is water present. In regions where there are distinct wet and dry seasons, an inspection ought to be made in each part of the year. The wet season inspection wil l be particularly useful in 20TRL Overseas Road Note 1, 3rd edition assessing the efficiency of drainage and in detecting cracking in bitumi nous surfaces, since this defect is more easily visible when the road surface is drying after rain . The network inspection will need to be completed in time for its results to be fed into the preparat ion of the budget estimate. Since most organisations prepare their estimates in the second half of t he financial year, the maintenance engineer has to make sure that the inspection programme is u ndertaken before this. 5 . 1 5 The day-to-day supervision of inspection work can be delegated to traine d technicians. But it is useful if the maintenance engineer participates personally in at leas t some of the visual inspections. This will ensure that maintenance works can be programmed e ffectively, based on personal familiarity with the road network. It also enables the quality of the inspections to be monitored. 5 . 1 6 Normally when inspecting a road section, the road is divided into subsec tions, typically 100 or 200 metres in length. The marker posts related to the roads register can be used as a reference, if they are present. An appropriate inspection method is described in Appen dix B, which makes use of standard forms. 5 . 1 7 Pre-printed forms are especially useful in providing a check-list that t ells the inspector what items are to be examined, and so reduces the possibility that significan t data may be omitted. The inspection method and forms shown in the appendix are intended only as a guide. In some cases, the maintenance engineer will have to adopt a standard procedure and rec eive an issue of standard forms from his organisation. In other cases, it may prove more useful to develop a specific inspection procedure and to draw up forms designed to suit the particula r road conditions in the locality. 5 . 1 8 Whatever form is used, it should be easy to understand and to complete. The road inspector should fill in the results on site, recording them accurately and legibl y. The forms should then be retained in the office to provide a permanent record of inspection resul ts. There is no need to make new, clean copies of forms completed on site: this wastes time and invol ves the risk of errors when information is transcribed. 5 . 1 9 It may be useful to summarise key results in the form of statistical tab les or diagrams – for example, graphs that show rates of deterioration over time. 21 TRL Overseas Road Note 1, 3rd edition 6 Determining options Basis of approach 6 . 1 Determining options for action involves selecting possible treatments th at can be used to cure defects and to restore conditions to the required level. In dealing with defects, the maintenance engineer must interpret the inspection results (Chapter 5) to decide w hen and where repairs are needed, and what form of maintenance activity is required. Like a doctor treating an illness, the engineer has to recognise the symptoms that indicate it is time to take remedial action. Rules should be set up to identify the stage or circumstance at which the maintenance engineer should intervene, and the action to be taken to stop further deterioration. The use of pre -defined rules for treatment selection ensures that a consistent approach is taken to specifying work s throughout the road administration. This helps to ensure that available funds are spent to g reatest effect, and that each road and part of the network receives its fair share of the budget. 6 . 2 These rules are known as ‘standards’ and ‘intervention levels’ . Ideally, they should be derived as part of the road maintenance policy framework. Standards and intervention levels provide the detailed operational targets to be worked to by individuals in the maintenance organisation. In some cases, they may be supported by legislation; in ot hers, they will be determined by the road administration itself. Each objective in the road maintenance policy may be supported by one or more standards or intervention levels; standards and intervention levels should, in turn, support an objective. 6 . 3 The road maintenance engineer needs to identify a range of treatments th at can be applied by the maintenance organisation to respond to road defects. These can be ba sed on the treatment options considered by the Note, which are listed in Tables 6.1 and 6.2 f or carriageways and off-road features respectively. These treatment activities are related to the gro ups, categories and treatment types given earlier in Table 2.1. 6 . 4 Two fundamentally different types of mechanisms are available for identi fying when treatments are necessary:  Scheduled – fixed amounts of work (such as a quantity in m 2/km) are specified per unit time period (such as one year), or work is specified to be undertaken at fi xed intervals of time; required maintenance activities are determined directly from applying th e maintenance standard  Condition-responsive – work is triggered when condition reaches a critical threshold (intervention level); required maintenance activities are identified a s a result of field inspections to determine where intervention levels are exceeded Scheduled treatments 6 . 5 Scheduled treatments are used where need is related to environmental con ditions, such as cutting back vegetation growth or cleaning culverts. The approach is als o appropriate where the deterioration rate is stable over time. Also, where deterioration rates are rapid, such as for the surface of gravel roads, it is impracticable to respond to defects asses sed as a result of condition surveys, so it is more convenient to schedule grading and dragging treat ments. Routine cyclic maintenance works, by definition, are carried out on a scheduled basis. 6 . 6 The frequency at which cyclic works are carried out will depend on the r equirements of the road maintenance policy, and will be influenced by level-of-service requ irements and resources available for maintenance. In the absence of local standards, those list ed in Table 6.3 can be used. 6 . 7 The requirements for grading on unpaved roads have to be determined inde pendently of the results of network inspections. The maintenance engineer must decide how many times during the year each unpaved road will need grading to provide an appropriate level -of-service under local conditions. This assessment should take account of a range of factors in cluding the type and size of the road material, the amount of traffic using the road, the local topog raphy, climatic regime and other physical features. If the engineer has access to a computer, and h as roughness measuring equipment available, the method outlined in Box 6.1 can be used to deter mine the optimum grading frequency for the road. If not, appropriate grading frequencies can be determined from Figure 6.1. In this figure, the solid line indicates the mean recommende d frequency, which is the one that should normally be adopted. Grading the road more frequently th an the mean will give road users a higher level of traffic-service: correspondingly, a grading frequency less than the mean will result in a lower level-of-service. 22TRL Overseas Road Note 1, 3rd edition Renewal. Overlay. Table 6.1 Maintenance and renewal treatments for carriageways Activities for different carriageway types Group and category Treatment typeAsphalt-surfaced Jointed-concrete Unpaved Routine unplanned Reactive. Periodic (planned). Preventive. Emergency.  Patching.  Crack sealing.  Joint repair.  Patching.  Crack sealing.  Local sealing.  Edge repair. Winter. Marking.  Fog seal.  Slurry seal. Resurfacing.  Regravelling.  Renew line markings.  Slab replacement.  Mill and replace.  Inlay.  Structural overlay. Pavement reconstruction. Routine planned. Cyclic.  Grading.  Dragging. Maintenance (Outside the scope of this Note).  Single surface dressing.  Otta seal.  Thin overlay.  Traffic accident removal.  Removal of broken-down vehicle.  Removal of landslide debris.  Removal of other debris on carriageway. 23 TRL Overseas Road Note 1, 3rd edition Table 6.3 Routine cyclic works frequencies Activity Frequency (no. times per year) 1 Grass cutting by machine 2 Grass cutting by hand 2 Machine cleaning of V-shaped side drains 2 Machine cleaning of U-shaped side drains 2 Manual cleaning of side drains 2 Cleaning culverts 2 Clearing bridge channels 1 Sign cleaning 1 Litter removal 1 Sweeping 2 1Frequency can be increased for roads carrying high traffic levels, and r educed for low traffic levels. Table 6.2 Maintenance treatments for off-road features Group and category Treatment type Activities for off-road features 1 Maintenance Routine planned.Cyclic. Grass cutting by machine. Grass cutting by hand. Machine cleaning of V-shaped side drains. Machine cleaning of U-shaped side drains. Manual cleaning of side drains. Cleaning culverts. Clearing bridge channels. Sign cleaning. Litter removal. Sweeping. 2 Routine unplanned.Reactive. Kerb repair or replacement. Shoulder repair. Footway repair. Side drain repair. Culvert repair. Minor bridge repairs. Sign repair or replacement. Guard rail repair. Retaining wall repair. 1 The maintenance and renewal of street lighting and other electrical app aratus are beyond the scope of this Note. 2 Sweeping is carried out at the edge channel of asphalt and concrete car riageways where kerbs are present. 24TRL Overseas Road Note 1, 3rd edition Box 6.1 Determining optimum grading frequencies Basis of the approach Ideally, an appropriate frequency of grading should be identified for ea ch individual road. However, it is more practical to determine optimum grading frequencies for groups of roads w ith similar traffic levels, similar materials types and sizes, and sharing similar topographic and other phy sical features. The more often a road is graded, the smoother its surface will become and the less deterioration there will be between gradings. The end result will be lower vehicle operating costs on the road. The aim is to choose a frequency of grading which minimises the sum of maintenance costs and vehicle operating costs durin g the maintenance year. HDM-4 analysis The easiest way to determine vehicle operating costs for particular grad ing frequencies is to use a road investment model such as HDM-4 (PIARC 1999). The model should be used to carry out analysis for each selected road surface material type, climate, road geometry and traffic level. Vehicle operating costs are then determined for a range of grading frequencies. The results should be plo tted in graph form. Curves such as those shown below should be obtained. The minimum cost plotted at each traffic level will indicate the optimum grading frequency. The grading frequency should be applied to particular roads on the network by select ing the traffic level on the graph closest to that found in the field. Different optimum values will be obtained fo r different traffic levels, and for roads with different material types, with different road geometry, and in different climatic areas. It is necessary to undertake separate analyses for each of these cases. Vehicle operating cost plus road maintenance cost Number of gradings/year Vehicles per day 200 150 100 75 5025 Optimum grading frequency line 25 TRL Overseas Road Note 1, 3rd edition Number of gradings /year 7 6 5 4 3 2 1 0 100 200 Annual average daily traffic (vehicles/day) Increasing level of service Mean recommended frequency Figure 6.1 Grading frequency chart (Source: derived from studies carried out by TRL) 6 . 8 Dragging needs to be done regularly where loose material lies on the roa d or where corrugations are liable to form. In the latter case, the operation may h ave to be repeated every few days. The maintenance engineer should determine the necessary frequency from a series of practical tests, by seeing how long it takes the corrugations to return after drag ging is carried out. The frequency will vary for different materials, design of drag, traffic vol umes and physical conditions. 6 . 9 The maintenance engineer should identify several roads that are represen tative of the network and arrange for a series of inspections to be performed immediately befo re the dates on which grading or dragging is scheduled. The inspection results will enable a c heck to be made on whether the frequencies of grading and dragging are appropriate. If, for example , a high degree of deterioration is still evident, the existing maintenance schedule should be adjusted to perform these activities more frequently. Condition-responsive treatment selection for unpaved roads 6 . 1 0 Regravelling is a periodic activity that will need to be performed whene ver the existing layer of gravel becomes unacceptably thin. If this layer is found to be less t han 50mm thick for more than 20 per cent of the length of the sub-section of road being inspecte d (Table 6.4), regravelling should take place. Appendix B includes advice on the inspection procedur e. 6 . 1 1 Dust control is normally undertaken by the application of one of the fol lowing liquids to the road surface:  Water.  Deliquescent salts, such as calcium chloride.  Organic compounds, including sulphite liquor, molasses, palm and other v egetable oils.  Mineral oils, such as waste fuel oils. The relief obtained by spraying roads with water is normally very short- lived, particularly in hot climates. Deliquescent salts function by retaining moisture in the surfa cing. Organic compounds and mineral oils function by coating and binding the dust particles. Use of such dust palliatives is only economic when they are available as waste materials and, in all cas es, their effectiveness is only temporary. When the cost of repeated applications is taken into acc ount, the application of the above liquids is likely to be more expensive than a more permanent treat ment, such as surface dressing. They may, however, be a useful expedient whilst awaiting more permanent action. 26TRL Overseas Road Note 1, 3rd edition Condition-responsive treatment selection for paved roads 6 . 1 2 Treatments are triggered, in most condition-responsive methods, whenever one or more defects exceed their respective intervention level. Most methods require that the severity and extent of defects are determined. Ideally, intervention levels should be derive d as part of the road maintenance policy framework, and will be influenced by level-of-service requirements, engineering issues and resources available for maintenance. Different se ts of rules may be needed for roads of different classes, recognising the dependency on the level- of-service expected from a particular road. 6 . 1 3 It is advisable always to adopt intervention levels suited to the partic ular local situation. A wide range of intervention levels could be adopted appropriate to local construction and maintenance standards, and to environmental conditions. In the absence o f local standards, use can be made of the intervention levels listed in Tables 6.5 to 6.7 for aspha lt-surfaced pavements, jointed-concrete pavements, and off-road features, respectively. The rec ommended levels are based on the assumption that the road network is already being maintained to a n adequate standard, and that sufficient resources are available to keep up this standard. In oth er words, they represent a target that the maintenance engineer should aim eventually to achieve. I n those cases where there are too few resources available to apply the recommendations, alternativ e levels should be adopted that are more appropriate to the workload and local capabilities. 6 . 1 4 Some of the intervention levels in these tables are expressed in quantit ative terms and require measurements to be made, as explained in Appendix B. Others involve simp ly a visual assessment. While the management system is being introduced, it is likely that the m aintenance engineer will have to rely mainly on the visual assessment of defects, but measurement techniques should be introduced as skills and resources permit. Diagnosing the cause of deterioration 6 . 1 5 It is important to identify the cause of deterioration and to put this r ight if possible, rather than just treating the symptom. For example, there is little point in co ntinually filling pot-holes in a road if they keep occurring because of poor drainage. Finding the real p roblem and focusing attention on its solution will produce a more cost-effective use of main tenance resources. It is therefore important that proper diagnosis of problems is undertaken by t he maintenance engineer, and Overseas Road Note 18 (TRL 1999) is a useful aid to this. 6 . 1 6 Some problems, of course, may be outside the scope of maintenance. For e xample, a road across flat country with inadequate drainage outfalls may experience bas e failure as a result of the capillary rise of water in the wet season. The only solution to the prob lem is to raise the level of the road. This would be a road improvement, not a maintenance operation. As such, it may warrant a special allocation of resources in accordance with the organisation’s procedures for road improvement work. Table 6.4 Maintenance intervention levels for unpaved roads Extent (per cent of Defect Level sub-section length) Action Notes Gravel thickness <50mm >20 R egravel Roughness (including corrugations). Surface distress (loss of See Paras 6.7-6.8. Grading. Scheduled (cyclic). camber, rutting, pot-holes, ravelling or loose material). Dust. –– See Para 6.11. 27 TRL Overseas Road Note 1, 3rd edition Table 6.5 Maintenance intervention levels for asphalt-surfaced pavements Extent (% of Climate/ Extent (% of sub-section traffic sub-section Defect Level length) categoryDefectlength) Action Notes Ravelling. Any. <10 All. – – Local sealing. A fog spray of emulsion may be sufficient to renew the surface. >20 All. – – Surface dress. Fatting-up or bleeding. – – All. – – No action. Local sealing or surface dressing may be required if the lack of skid resistance is a problem. In this case, the excess binder must be burned off first. Sanding is appropriate when live (shiny) bitumen is on the surface. Shoving. Major.Any. – – – Further investigation. – Pot-holes. Any. – All. – – Patch. Extensive pot-holing may result from lack of effective maintenance or rapid deterioration of the road structure or surfacing. The cause must be determined and appropriate action taken. Trench/ utility opening. Poor reinstatement. – All. – –Reinstate. Cost of work should be charged to utility company. Edge damage. Erosion from >20 All. – – Patch road edge and If the failure is severe or persists, original edge repair shoulder. reconstruct the shoulder. >150mm. Edge step. >50mm >50 All. – – Reconstruct shoulder. – Worn road markings. Visual assessment – – – – Renew markings. – (engineering judgement). Continued .... 28TRL Overseas Road Note 1, 3rd edition Table 6.5 (Continued) Maintenance intervention levels for asphalt-surf aced pavements Extent (% of Climate/ Extent (% of sub-section traffic sub-section Defect Level length) categoryDefectlength) Action Notes Wheel track rutting <10mm – Rainfall Wheel <5 Seal cracks. (surface dressing on > 1500mm/yr track granular base). OR cracking. >5Surface dress. Single seals are often insufficient Traffic > 1000vpd Non-wheel <10 Seal cracks. track cracking. >10 Surface dress. See note above. Rainfall Wheel track <10 Seal cracks. <1500mm/yr cracking. AND >10 Surface dress. See note above. Traffic <1000vpd Non-wheel <20 None. track cracking. >20 Surface dress. See note above. 10-15mm >10 All. Any – Treat cracks depending If rate of change of rut depth is slow. cracking. on extent as above. Further investigation. If rate of change of rut depth is fast. >15mm <10 All. Cr acking –Patch. only associated with local ruts. Other – Patch excess rutting cracking. and treat cracks depending on extent as above. >10 All. Any – Further investigation. cracking. Continued .... 29 TRL Overseas Road Note 1, 3rd edition Table 6.5 (Continued) Maintenance intervention levels for asphalt-surf aced pavements Extent (% of Climate/ Extent (% of sub-section traffic sub-section Defect Level length) categoryDefectlength) Action Notes Wheel track rutting <10mm _ Rainfall Any <5 Seal cracks. (asphaltic concrete on >1500mm/yrcracking. granular base). OR 5-10Surface dress. Single seals are often insufficient for Traffic wide cracks. >1000vpd >10 Further investigation. Rainfall Any <10 Seal cracks. <1500mm/yr cracking. AND 10-20 Surface dress. See note above. Traffic <1000vpd >20 Further investigation. >10mm <5 All. Cr acking –Patch. only associated with local ruts. Other – Patch excess rutting cracking. and treat cracks depending on extent as above. >5 All. Any – Treat cracks depending If rate of change of rut depth is slow. cracking. on extent as above. Further investigation. If rate of change of rut depth is fast. Continued .... 30TRL Overseas Road Note 1, 3rd edition Table 6.5 (Continued) Maintenance intervention levels for asphalt-surf aced pavements Extent (% of Climate/ Extent (% of sub-section traffic sub-section Defect Level length) categoryDefectlength) Action Notes Wheel track rutting <5mm – Rainfall Any <10 Seal cracks. Includes reflection. (asphaltic concret e or >1500mm/ yr cracking. surface dressing on OR >10 Seal cracks and stabilised road base). Traffic surface dress. >1000vpd Rainfall Any <20 Seal cracks. <1500mmcracking. AND >20 Seal cracks and Traffic surface dress. <1000vpd 5-10mm >10 All. Any – Treat cracks depending If rate of change of cracking. on ex tent as above. rut depth is slow. Further If rate of change of rut depth is fast. investigation. >10mm <5 All.Cracking – Patch. only associated with local ruts. Other – Patch excess rutting cracking. and treat cracks depending on extent as above. >5 All. Any – Further investigation. cracking. ‘Further investigation’ should be undertaken using the method desc ribed in Overseas Road Note 18 (TRL 1999) 31 TRL Overseas Road Note 1, 3rd edition Table 6.6 Maintenance intervention levels for jointed-concrete pavements Defect Level Extent Action Notes Cracking of slab. Individual cracks Cracking in one or Concrete crack Cracking not wide enough to more directions, sealing.associated insert a coin. including corner with local cracks. depressions. Inter-connected <50% of slab affected Concrete patching. cracking associated and/or loss of material with local from surface of slab, depressions. leaving coarse aggregate proud of the matrix, or causing loss of coarse aggregate. Loss of material Extending more than Extending more than Concrete joint repair. from joint or arris. 100mm from the joint. 300mm along the joint. Steps at joints. >25mm– Concrete slab replacement. Local depressions. – >50% of slab affected. Worn road markings. Visual assessment (engineering judgement). Renew markings. 32TRL Overseas Road Note 1, 3rd edition Table 6.7 Maintenance intervention levels for off-road features Feature DefectLevel/extent Action Notes Kerb. Missing or Visual assessment Kerb repair or damaged.(engineering replacement. judgement). Verge. High vegetation. Interferes with Grass cutting. 1 line of sight. Shoulder. Deformation Hazardous to traffic, Shoulder repair or scour. or endangering the (fill/patch). structure of the road (engineering judgement) Extent >20% sub-section. Extent >50% sub-section. Reconstruct shoulder. Footway. Cracking or Sudden trips >25mm. Footway settlement. repair. Side drains. Silted.Ditch depth reduced Clean side Drainage faults should to <1m or blocked to drains. 1 be corrected before the the extent that the free wet season starts. flow of water is impeded. Standing water Visual assessment Side drain repair after rain. (engineering judgement). (realign to correct gradient). Scoured or Visual assessment Side drain repair Scour can develop damaged. (engineering judgement). (build check-dams rapidly, and can cause and fill). severe damage tostructures; repair is urgent. Culvert, including Silted.Blocked to the extent Clean culvert. 1 invert and outfall. that the free flow of water is impeded. Scoured or Visual assessment Culvert repair. damaged. (engineering judgement). Road sign. Dirty.Unreadable. Sign cleaning. 1 Includes road markings, warning and information signs, bollards, marker posts, etc. Damaged or Visual assessment Sign repair. corroded. (engineering judgement). Missing. – Sign replacement. Continued .... 33 TRL Overseas Road Note 1, 3rd edition Specifying the work required 6 . 1 7 The maintenance engineer should examine the completed inspection forms ( Chapter 5) and compare the inspection results with intervention levels of the type reco mmended in Tables 6.5 to 6.7. The maintenance needs of each sub-section of the road network can t hen be determined, and the work required specified. The necessary action should be marked on th e inspection forms, preferably in a different colour from that used for the survey results. The forms will provide a permanent record of maintenance requirements. Table 6.7 (Continued) Maintenance intervention levels for off-road fea tures Feature DefectLevel/extent Action Notes Guard rail. Damaged Hazard to traffic, or Guard rail repair. or missing. failing to performproper function. Retaining wall. Damaged.Hazard to traffic, or the Retaining wall structure is in danger repair. of collapse. Bridges and other Silted or blocked. Visual assessment Clean out channel. Drainage faults should structures. 2 (engineering judgement). be corrected before the wet season starts. Scoured. Visual assessment Repair (build scour Scour can develop (engineering judgement). control works rapidly, and can cause and fill).severe damage to structures; repair is urgent. Structural damage. Visual assessment Repair. (engineering judgement). 1Normally a cyclic activity, but action should taken if inspections show that intervention levels are exceeded.2Although the maintenance of bridges and structures is beyond the scope o f this Note, they should be inspected at the same time as other road features, and the defects listed recorded fo r action; for the more serious defects, follow-up inspections should be undertaken using the procedures in Overs eas Road Note 7 (TRRL 1988). 34TRL Overseas Road Note 1, 3rd edition 7 Choosing actions Selection from among options 7 . 1 The treatment selection process, described in Chapter 6, may indicate a number of different treatment options for an individual section of road. The options may eac h have a different cost, and a different treatment life. The process of choosing the appropriate action has to take account of the options available on each section of road, bearing in mind that there is unlikel y to be sufficient budget to fund all of the treatments needed across the network. The process therefore i nvolves the following steps: i Estimation of resource requirements, depending on the treatment and choi ce of work method. ii Costing these requirements. iii Grouping works into appropriate ‘packages’. iv Prioritising works to determine which can be carried out within the avai lable budget. Resource estimation Choice of work method 7 . 2 The approach to estimating resources will depend on the work methods ado pted for carrying out the physical road works. At this stage, therefore, choices have to b e made between:  Technology – whether labour or equipment-based methods will be used f or different activities.  Procurement method – whether activities are to be carried out by cont ract or using in-house labour resources. There is some inter-relationship between these choices. For example: if procurement is to be by contract, then the choice of technology is a matter for the contractor t o decide; however, the detailed procurement method may depend on whether the contract is to be let to a relatively large equipment- based contractor or to labour-based ‘lengthworker’ contractors. Th e methods of resource estimation will differ depending on whether work is to be undertaken by contract or using in-house staff. Choice of technology 7 . 3 There are some activities that can only be done by manual labour; there are others where plant and machinery are essential; but many activities offer the option of either method. Trying to combine manual labour and machinery on the same activity will normally l ead to inefficiency. The maintenance engineer may need to choose between a labour-based and an eq uipment-based method for each activity. In making this choice, account should be taken of the following factors:  technological appropriateness;  cost-effectiveness;  availability of labour;  availability of equipment;  use of domestic resources. 7 . 4 Table 7.1 gives an assessment of the technological appropriateness of va rious maintenance activities for the use of labour-based and equipment-based methods. 7 . 5 It is likely to be more cost-effective to use labour-based methods where real labour costs are less than about US$4-6 per day. At higher rates, equipment-based methods are likely to be more competitive. Where labour-based methods are cost-effective, the followin g should be noted: 35 TRL Overseas Road Note 1, 3rd edition Table 7.1 Technological appropriateness for use of labour and equipment- based methods Potential for: Activity Labour Equipment Routine cyclic Grading (unpaved). Impracticable. Good – skilled. 1, 2 Dragging (unpaved). Impracticable.Good. Grass cutting. Good.Good. 3 Ditch cleaning and cutting. Good. 4 Good. 4 Cleaning of culverts and bridges.Good.Poor. Sign cleaning. Good.Impracticable. Litter removal. Good.Fair. Sweeping. Good.Good. Routine reactive Patching (asphalt and concrete). Good.Poor. Crack sealing (asphalt and concrete). Good.Poor. Local sealing (asphalt). Fair.Poor. Edge repair (asphalt). Good.Fair. Joint repair (concrete). Good.Fair. Kerb repair or replacement. Good.Fair. Shoulder repair. Good.Fair. Footway repair. Good.Fair. Side drain repair, including building scour controls. Good. Poor. Minor repairs to culverts and bridges. Good.Poor. Sign repair or replacement. Good.Poor. Manufacturing signs. Good 5 – skilled. 1 Fair. 5 Guard rail repair.Good.Poor. Retaining wall repair. Good.Poor. Periodic Fog seal. Fair.Good – skilled. 1 Slurry seal. Fair – skilled. 1 Good – skilled. 1 Single surface dressing.Fair – skilled. 1 Good – skilled. 1 Stockpiling chippings.Poor. Good. Thin overlay. Impracticable.Good. Regravelling including stockpiling gravel. Fair.Good. Renew road line markings. Fair.Good. Renewal Structural overlay (asphalt). Impracticable.Good – skilled. 1 Mill and replace (asphalt). Impracticable.Good – skilled. 1 Inlay (asphalt). Impracticable.Good – skilled. 1 Slab replacement (concrete). Good.Good – skilled. 1 1 The expression ‘skilled’ implies that specific training of operati ves is essential. 2Towed-graders can be substituted for motor graders for this activity, pr ovided deterioration is not too great. 3The potential in this activity is dependent on the width of the shoulder and presence of obstructions such as road furniture and culvert headwalls. 4The potential in these activities is dependent upon suitable design of t he ditch cross-section – ‘V’-shaped ditches are suitable for maintenance by grader, whereas flat bottomed ditches ar e suitable for maintenance by hand or mechanical back-hoe. 5Some methods of manufacture may require the use of specialised plant (e .g. vacuum-application of reflective sheeting to sign plates). 36TRL Overseas Road Note 1, 3rd edition  Tractor-trailer haulage is likely to be cost-effective for haul distance s up to about 10km, and truck-based haulage should be used for distances greater than this.  Labour-based surface patching operations on unpaved roads are only justi fied when traffic levels are below about 50 vehicles per day; above this traffic level, me chanical grading is necessary (possibly using towed-graders, which can be very cost-effecti ve). Note that, although machinery normally produces a truer surface and a mo re consistent finish than manual labour, this may not always be required. For example, it would be difficult to find any economic justification for giving low-volume roads the close tolerances of level and smoothness that machinery can achieve. 7 . 6 Labour-based methods are only appropriate where there is an abundant sup ply of labour available. The supply of labour is likely to be a problem where populati on density is less than about five persons per square kilometre. In addition to this demographic factor, la bour availability is also affected by the availability of alternative employment; seasonal and climatic fac tors have an impact in some areas which might result in available labour being scarce: harvest times being an obvious example. There are also socio-cultural factors that result in labour not being av ailable or willing to work on roads, even though it is relatively plentiful. Decisions must be taken on a dis trict-by-district basis. 7 . 7 Many countries are faced with major problems over the availability of eq uipment, in particular the procurement of spare parts and the maintenance of mechani cal equipment. This results in a low level of equipment availability that restricts the amou nt of road maintenance that can be carried out. Where there are difficulties keeping mechanical equi pment operational, there is a strong case for using labour-based methods, wherever possible. 7 . 8 Simple equipment that is manufactured domestically should be easier to r epair and keep operational than imported equipment. Tractor-based technology is likely to deliver higher equipment availability than the use of heavy equipment-intensive road ma intenance. This approach is also less demanding on the use of imported resources, thus conserving foreign exchange. 7 . 9 The above considerations should be used to determine which choice of tec hnology is the most appropriate for individual maintenance activities. Other factors ma y also have to be taken into account and, in some cases, the maintenance engineer may not be empowere d to make this choice. Procurement by contract 7 . 1 0 Traditionally, implementation of maintenance has been undertaken by the road administration itself. However, increasingly, work is procured under com petitive contract arrangements to seek benefits in both effectiveness and efficiency. Unde r a contract system, the maintenance engineer enters into a formal agreement with a contractor fo r undertaking specific maintenance or renewal works. Normally the contractor should be chosen t hrough competitive tendering from a number of bidders. Some different types of contracts ar e described in Chapter 8. If organisational policies permit, consideration should be given to unde rtaking maintenance and renewal works using competitive contracts. 7 . 1 1 For larger contracts for renewal or periodic maintenance, it is common f or the maintenance engineer to appoint a firm of consulting engineers to assist in project administration and to supervise the work of the contractor. One advantage of a civil works con tract is that responsibilities between the three parties – the ‘employer’ (the maintenance en gineer), the ‘contractor’ and the ‘engineer’ (the consulting engineer) – are well-defined. 7 . 1 2 Contracting-out work can have the advantage of relieving pressure on the organisation’s labour resources and it can offer a high level of efficiency at a compet itive cost. The detailed tender documents for these contracts need to include all details about the trea tment design (see Chapter 8), so the method enables fair competition between potential contractors. Th e employer benefits by knowing the financial obligation before commencement of works. Drawbacks of works contracts are that procurement tends to be more time consuming than other project implementation methods because of the need for the detailed design to be substantially complete . The road administration will have to prepare detailed contract documents, set up a tendering pro cedure and provide contract supervision – all of which may require a substantial amount of time a nd effort on the part of its staff. There is also a risk that contractors bidding for maintenance wor k on a regular basis may 37 TRL Overseas Road Note 1, 3rd edition introduce ‘price-fixing’ to increase their profitability, and so i nvolve the organisation in higher costs. On the other hand, time extensions, claims, and the like are safe guarded as a result of the detailed preparation. The maintenance engineer will have to weigh up the se factors in relation to the capacities of his organisation and the performance of local contract ors. 7 . 1 3 The activities in Table 7.2 should present no significant problems of ad ministration or quality control if contracted out on the basis of competitive tenders. Specialis t contractors can also be brought in to undertake the supply and maintenance of machinery and vehi cles. The maintenance engineer should be satisfied that any contractor invited to tender for a job is capable of completing it satisfactorily, has the necessary personnel and equipment available, and is sufficiently knowledgeable about estimating procedures and current market rates to su bmit realistic prices. In-house works 7 . 1 4 In-house implementation (also known as ‘force account’ or ‘dir ect labour’) is often used for road maintenance, but its use is less common for renewal works. As the d esign, works execution and supervision are handled by the road administration’s own organisa tion, disagreement with other parties does not occur, and the personnel involved are familiar wi th the requirements, policies and procedures related to the works. It is often possible to save time b y adopting an in-house approach because works can commence as soon as funding becomes available , even if this is before the design is complete. 7 . 1 5 A disadvantage is that government accounting procedures make it difficul t to achieve adequate internal cost control, and this tends to result in higher overa ll works costs than for other execution methods. Quality control is also difficult to make effective. It can be difficult to hold anyone accountable for delays and poor quality works, given that the sam e organisation is both executing and supervising the works. There is often a reluctance to repl ace poor quality works because of the additional costs involved. Work is often implemented in a manner that makes maximum use of available resources (work force, equipment and materials ), rather than applying rational and efficient work methods. This leads to inefficiency. Table 7.2 Typical activities suitable for undertaking by contract Maintenance and renewal activities Routine cyclic Grading and dragging (unpaved). Grass cutting and sweeping. Periodic Resealing: surface dressing, thin overlay, fog and slurry sealing (asph alt). Renewal of road markings. Regravelling (unpaved). Renewal Structural overlay, mill and replace, inlay (asphalt). Slab replacement (concrete). Supply of materials Processed and natural gravels and aggregates. Bitumen, cement and lime. Precast concrete products. Steel reinforcements. 38TRL Overseas Road Note 1, 3rd edition Estimating 7 . 1 6 The maintenance engineer should make an estimate of the likely cost of w orks, irrespective of whether this is to be carried out by contract or using in-house resou rces. This information is used as part of the programming and budgeting process. It is good practice to develop ‘performance standards’ for each works activity. An example is given in Box 7.1. A performance standard defines the materials, labour and equipment required for each works acti vity, and indicates the productivity and work accomplishment to be anticipated. They can be used to develop reliable unit rates for all activities to be undertaken. However, developing appropria te and reliable performance standards is a substantial task and relies on good information about wor ks outputs being collected over a reasonable period of time. 7 . 1 7 It is normally relatively easy to estimate directly the quantities of ma terials needed for a works activity. Where the extent of the work can be defined precisely – for example, in the case of surface dressing or regravelling – quantities are determined in accor dance with standard engineering practice. For other activities where requirements are less e asy to define, such as edge repairs to bituminous surfaces, patching pot-holes and repairing defects in culverts, quantities are gauged on the basis of inspection results. The method can again follow s tandard practice, but these estimates will of necessity be less precise. The quantities determined s hould include an allowance for any emergency work that may be needed, for example in repairing stor m damage to culverts or vehicle damage to bridge parapets. 7 . 1 8 The amounts of labour and equipment required will depend on the method u sed in carrying out the work. These also depend on the productivity levels anticipated from different maintenance activities. The productivity of an activity can vary considerable from country-to-co untry, but Table 7.3 can be used as a guide. It should be noted that the values in this table make n o allowance for time that is not spent actually working, including non-productive time due to broken down or non-available equipment. Non-productive time can build up significantly during mainten ance operations, and it should be an aim of management to reduce it to a minimum. 7 . 1 9 Table 7.3 indicates the outputs of work that can be expected from teams engaged on normal maintenance activities, using manual labour or machinery, as appropriate . Each output is expressed as a range: the amount of work that a team in fact achieves should lie w ithin this range, depending on local conditions. For example, a labour-based approach to clearing si de drains is likely to involve between four and ten workers using simple hand equipment, and th e team can be expected to clear between 30 and 60 metres of drain per worker-day. A machinery-b ased approach to the same task will reduce the labour requirement to two or three labourers, using a grader and shovels and, as a team, they will be able to clear between four and seven kilome tres per day. Many activities need only simple equipment, such as picks and shovels. The ma intenance engineer should use this table as a guide to assessing the levels of productivity associated with various activities, and estimating the amount of labour required for each. Costing 7 . 2 0 Figure 7.1 shows how a standard form can be used to record the resources required for each activity and their estimated costs. A blank copy of the form is included in Appendix D. 7 . 2 1 The maintenance budget may include overheads allocated by the road admin istration to various activities other than actual maintenance operations. The mainten ance engineer must take these sums into account when calculating the resources available for roa d works. The following items may be involved:  Establishment – staff and buildings for managers.  Road network management activities – strategic planning, programming, surveys, design and procurement, operations management.  Administrative tasks – records, accounts and personnel management.  Training.  Emergencies – some funds may be set aside to cover the costs of reope ning roads after emergencies or accidents.  Technical assistance – e.g. advice to other organisations or local co mmunities. 39 TRL Overseas Road Note 1, 3rd edition Box 7.1 Sample output of a performance standard OPERATIONS SYSTEM PERFORMANCE STANDARD Revision C: 01 April 1997 Page 1 of 1 WORKS ITEM CODE: LG-112 DESCRIPTION: Single surface dressing DEFINITION Application of one coat of surface dressing consisting of a layer of bituminous binder on prepared surface covered by a layer of stone chippings RESTORATION STANDARD Uniform appearance with stone to stone contact RELEVANT SPECIFICATION LGS 11.22, LGS 11.34 - 11.37 UNIT OF MEASUREMENT m 2 AVERAGE DAILY PRODUCTION 2 000 m 2 WORKS METHOD 1) Establish traffic control - refer to Roadworks Signing Guide 2) Inspect pavement and mark out all areas of repairs if this has not already been done 3) Repair potholes and edge damage (see LG-008 and LG-009) 4) Remove all loose material with hand or mechanical brooms 5) Confirm and check all plant is working before commencing surfacing operation 6) Apply bitumen using distributor ensuring even spread (confirm rate of 1.0kg/m 2 with Supervisor) 7) Spread aggregate uniformly (confirm rate of 14kg/m 2 with Supervisor) 8) Roll to embed aggregate with 8-10 tonne rubber-tyred roller or other approved plant 9) Brush to remove surplus aggregate using mechanical broom or manually 10) Remove traffic control, leaving loose chipping warning signs if necessary ESTIMATED ITEM COST LABOUR NUMBER RATE AMOUNT Foreman/Supervisor 1 195.00 195.00 Operator 5 150.00 750.00 Semi skilled labourer 2 135.00 270.00 Labourer 6 125.00 750.00 EQUIPMENT Bitumen distributor 1 375.00 375.00 Road roller (8/10t) 1 400.00 400.00 Loading shovel (1.5m 2) 1 550.00 550.00 Tipper truck (5/10t) 1 410.00 410.00 Gritter 1 100.00 100.00 Signs and traffic control 1 50.00 50.00 Mechanical broom 1 200.00 200.00 MATERIALS UNIT QUANTITY 10mm aggregate tonne 28.0 25.50 714.00 MC3000 bitumen kg 2000.0 0.24 480.00 Diesel litre 25.0 0.91 22.75 TOTAL 5266.75 ESTIMATED UNIT RATE 2.63 40TRL Overseas Road Note 1, 3rd edition Table 7.3 Examples of work outputs from activities Resource requirements Range of Activity Personnel Equipment Materials Output unitoutputs Clearing side 4-10 Shovels, cutlasses, – m/worker-day.30-60 drains by hand. picks . Clearing side 2-3 Grader, shovels. – km/day. 4-7 drains by machine. Re-excavating 2-10 Picks, shovels.– m/worker-day. 8-15 side drains. Clearing 2-4 Shovels, head-pans/ – no/worker-week. 2-4 culverts. w heelbarrows. Minor repairs 2-4 Masons’ tools. Cement, aggregate,no/worker-week. 2-10 to culverts. sand. Major repairs To be assessed– worker-day. – to culverts. for each job. Making culvert 4-10Moulds, mixer, shovels. Cement, stone, sand, no/day. 5-10 rings (1m reinforcement. diameter × 1m long). Grading 2 Grader, camber board, – pass-km/day. 1 20-50 unpaved spirit level. surfaces. Dragging 1 Tractor and drag. – pass-km/day. 1 20-50 unpaved surfaces. Patching 5-7 Pedestrian roller or hand Premix or gravel, m 3/worker-day. 0.5-0.8 bituminous rammers, brushes, picks, bitumen emulsion, surfacings. shovels, watering cans. chippings or washed gravel. Filling gravel 5-7 Pedestrian roller or handGravel. m 3/worker-day. 0.6-1.2 surfaces. rammers, brushes, picks, shovels, watering cans. Filling earth 4-5 Hand rammers, brushes, Selected earth. m 3/worker-day. 0.9-1.5 surfaces picks, shovels. and slopes. Grass cutting 2-10Cutlasses. –m 3/worker-day.300-800 by hand. Continued .... 41 TRL Overseas Road Note 1, 3rd edition Table 7.3 (Continued) Examples of work outputs from activities Resource requirements Range of Activity Personnel Equipment Materials Output unitoutputs Grass cutting 1-2 Tractor/mower. – km/ day. 10-20 by machine. Repairing and 2-3 Masons’ tools, painters’. Cement, stone, sand, no/worker-day 4-8 replacing traffic tools, shovels. paint, reflective signs. paint. Road markings. 2-4 – Road paint.m/worker-day.50-200 (hand painting). Stockpiling 10-20 Picks, shovels. – m 3/day.450-500 gravel by hand. Stockpiling 4 Bulldozer, loader.Gravel. m 3/day.300-350 gravel by machine. Regravelling 12-20 1 grader,Gravel.m 3/day.300-350 gravel surfaces. 8 tippers, 1 loader, 1-2 water tankers, 1 roller Surface dressing. 15-20 2 1 distributor, Bitumen, chippings.lane-km/day.2.5-4.0 1 roller, 3 tippers, 1 gritter, 1 loader. 1‘Pass-km’ is the actual distance the grader travels while working. 2+ 10 additional if no loader is available + 10 additional if no gritter. 42TRL Overseas Road Note 1, 3rd edition Figure 7.1 Example of a resource requirements form District: Period: Section: Budget: Length: Width: km/metres metres Resource requirements and cost estimate Activity: Resource Quantity Unit Rate Cost Labour Equipment Materials Sub-total Sub-total Total Supervisors Unskilled Skilled 1 2 3 4 5 6 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 Worker-day Worker -day Worker -day Worker -day Worker -day Worker -day Worker -day Worker -day Central Nov/Dec 2003 Regravelling C231 Recurrent 25 6 2 no. 8 no. Grader operator Roller operator Truck driver Grader 6 -8 tonne roller Dump truck 120 480 60 120 60 7.80 2.52 5.12 4.38 4.12 936.00 1209.60 307.20 525.60 247.20 500 1000 600 25.00 10.00 9.00 12500 10000 5400 hr. hr. hr. 10000 200 20000 m 3 3225.60 6820 20000 29745.60 Th. E. Engineer Signed ……………………………………………… .. Sub-total 43 TRL Overseas Road Note 1, 3rd edition 7 . 2 2 Traditional engineering unit pricing techniques are normally applied to the resource estimates to develop the anticipated works costs for programming and budgeting pur poses. Providing that resources have been estimated using the methods described above, then co sting should be relatively straightforward. Expected values and timescales should reflec t past experience of actual achievement on completed works with similar characteristics. However, th ere are difficulties associated with costing methods because there are many variables that af fect works cost in different situations and circumstances. More details of cost-estimating techniques appropriate to road maintenance works can be found in Road maintenance management: concepts and systems (Robinson and others 1998). This describes issues of where and how cos t data can be obtained, and the reliability of different cost-estimating methods. 7 . 2 3 Note that, at the ‘programming’ stage, it would be normal to use o nly unit rate costing methods applied to works ‘types’ (see Table 2.1). More detailed costing methods should be used at the works implementation stage, once a budget has been awarded. Works packaging 7 . 2 4 When works are to be undertaken by contract, there may be a minimum size of works for which the use of a contract is cost-effective. Also, where treatment len gths are relatively short, it may sometimes be more cost-effective to combine treatment lengths, even of a different treatment type, into contract packages. These same considerations apply even if wo rks are to be undertaken in-house, if the most cost-effective implementation is to be achieved. T herefore, the way that works are packaged will affect their costs. 7 . 2 5 A simple method of contract packaging is described in Box 7.2. This uses decision rules to combine road lengths of uniform defectiveness into ‘treatment lengths ’ on which it is cost-effective for works to be carried out. On any length of road, the aim is to group projects or schemes containing the same or compatible works on adjacent road lengths. This m ay involve applying more expensive treatments than would otherwise be justified on some sect ions of road. The process may be considered in terms of seeking economies of scale in terms of tre atment cost. Box 7.2 Example of approach to contract packaging Consider the three sections of road A, B and C, shown below: Sections A and C require an overlay at a fixed cost of $F1, and a variab le cost of $V1 per unit area. Section B requires surface dressing at a fixed cost of $F2, and a variable cost of $V2 per unit area. Therefore, the cost of applying separate treatments to the three sections is: ($F1 + $V1.areaA) + ($F2 + $V2.areaB) + ($F1 + $V1.areaC) However, if an overlay were to be applied throughout, then the cost woul d be: $F1 + $V1(areaA + areaB + areaC) It follows that if ($F1 + $F2)/($V1 - $V2) ≥ areaB then it is economic to overlay all sections, rather than to overlay A an d C, and to surface dress B. Section A Section B Section C Adjacent road sections requiring different treatments 44TRL Overseas Road Note 1, 3rd edition 7 . 2 6 Works should also be packaged into lots to suit contracting capability a nd capacity. Packaging should also be considered for works to be undertaken by in-hou se units. The size, content, start date and duration of each package depend on a number of f actors:  The size of packages can be chosen to provide a spread of work across co ntractors of different size and resource capabilities; for example, equipment-based and labour- based contractors.  Separate packages may need to be prepared for routine, periodic and rene wal works: – because funds come from different budgets; – to attract contractors of different size; – term-contracts are relatively simple to set up for routine works, wherea s periodic and renewal works are undertaken as discrete projects.  A variety of work in a particular location can be packaged together to r educe contract mobilisation costs.  A small number of large packages is normally easier and cheaper to admin ister and manage than a large number of small contracts. Priority assessment Purpose 7 . 2 7 It is likely that resources will be limited, and decisions will therefor e be needed on the most effective way of applying them. This means working out an order or prior ity, with the operations that have the strongest claim on resources placed at the head of the lis t and those that have least claim placed at the end. This part of the Note gives an example method t hat will enable the maintenance engineer to identify priorities objectively and consistently . The method is straightforward: it simply relates the importance of the maintenance act ivity to the importance of the road. It asks two basic questions:  How critical is a particular maintenance activity to the traffic perform ance of the road?  How significant is the particular road as a transport link? The maintenance engineer should review this method and make any adaptati ons to it that are necessary to meet particular local circumstances. Example method 7 . 2 8 Maintenance activities may be ranked in the order of importance shown in Table 7.4. 7 . 2 9 The roads that carry the heaviest loads of traffic are normally the most important parts of the network from an economic standpoint. They are also the roads liable to d eteriorate most rapidly from wear and tear. There may also be roads with relatively low levels o f traffic, which nevertheless have key strategic importance because of the places they li nk, such as international airports, important government buildings, or key industrial facilities. Generally, there will be only one or two such roads in any district. Since it is vital to keep these s trategically important roads in good condition, it makes sense to give them top priority for maintenance work. 7 . 3 0 The remainder of the network should be classified by the level of traffi c on each road. This level is usually expressed in terms of the estimated annual average daily traf fic (AADT); i.e. the total traffic in both directions during the year, divided by 365. Estimates are needed fo r traffic flow on every part of the network, including minor and unpaved roads. The estimate is most rel iable if it is derived from actual traffic counts. However, it is only necessary for maintenance prioritisa tion purposes to group roads into traffic ‘bands’. Simple traffic count procedures for this are desc ribed in Appendix C. 7 . 3 1 Table 7.5 sets out a simple hierarchy of roads by order of importance ba sed on traffic level. It is meant as an example, which the maintenance engineer can adapt to refl ect the character of his road network and the general levels of traffic. 45 TRL Overseas Road Note 1, 3rd edition Table 7.4 Maintenance activities by order of importance Hierarchy of maintenance category/type W ork activities Notes 1. Emergency work. Emergency repairs to blocked or Emergency works of this type are where impassable roads. there is a danger-to-life. As such, they Removal of traffic accidents, demand top priority. Past experience will broken-down vehicles, landslide or indicate the scale of the resources that other debris on the road. need to be set aside for these activities. 2. Routine drainage work. Cleaning of side drains, culverts and This work always deserves high priority bridge channels (cyclic). because neglected drainage can rapidly Side drain or culvert repair; minor lead to deterioration of the whole road, bridge repair (reactive). especially where defects affect the direct entry of water into the pavement. It should not be assumed that all drainage work must take precedence over all other work. The key point is that repairing surface defects caused by poor drainage will be a waste of time and effort unless the drainage is put right first. 3. Routine pavement work. Patching, crack sealing, local sealing The importance of this work reflects its and edge repair (asphalt). impact on the structural integrity of the Patching, crack sealing and joint road and on traffic safety. repair (concrete). Grading and dragging (unpaved). 4. Periodic work. Fog and slurry seal, surface dressing Periodic work can be treated as a series of and thin overlay (asphalt). distinct projects that have to compete for Road line marking (asphaltthe resources available and can be and concrete). undertaken separately, deferred or Regravelling (unpaved).brought forward as required. 5. Other routine work. Grass cutting, sign cleaning, litter This work is mainly of an removal, sweeping (cyclic). ‘environmental’ nature and is of Kerb repair or replacement, shoulder relatively low priority. and footway repair, sign repair or replacement, guard rail and retaining wall repair (reactive). 6. Renewal work. Structural overlay, mill and replace, Renewal work has high unit cost and has and inlay (asphalt). low priority to avoid swallowing-up large Slab replacement (concrete). portions of the maintenance budget. Works can be treated as a series of distinct projects, as for periodic works (above). 46TRL Overseas Road Note 1, 3rd edition Table 7.5 Road traffic levels by order of importance Importance Traffic level (vehicles/day) Surface type 1 (Strategic roads) – 2 Greater than 1000 Asphalt and concrete. 3 500 – 1000 Asphalt and concrete. 4 200 – 500 Asphalt and concrete. 5 Greater than 200 Unpaved. 6 Less than 200 Asphalt and concrete. 7 50 – 200 Unpaved. 8 Less than 50 Unpaved. 7 . 3 2 An axle-load survey, in addition to traffic counts, may be justified if the traffic composition on a particular road is believed to be significantly different from that on the network as a whole – for example, on a road that carries large numbers of heavy freight vehic les. The survey can be completed in a few days using a portable weighbridge. Guidance on proced ures for axle-load surveys is included in Overseas Road Note 40 (TRL 2003). 7.33 Table 7.6 is an example of a matrix that can be used to assign priority numbers to the various maintenance activities. The matrix is defined in terms of the hi erarchies of maintenance activities and traffic from Tables 7.4 and 7.5. Maintenance activities a re numbered from 1 (highest priority – emergency maintenance on strategic roads) to 48 (lowest priority – renewal works on unpaved roads with very low levels of traffic). The matrix is designed to ensure that every road in the network receives at least the minimum maintenance need ed to keep it operational, while at the same time focusing routine pavement and period ic maintenance on the economically important roads with high traffic levels. As noted above, s trategically important roads have absolute priority for resources, even where renewal works are concerned. 7 . 3 4 The maintenance engineer should develop a matrix appropriate to local co nditions. This can then provide a master list identifying, in order of priority, all the wo rks that need to be done on the network. While the numbering scheme in Table 7.6 is a rational and consi stent order of priority, it is not meant to be inflexible. There may well be local conditions of soil t ype, topography and climate that influence maintenance requirements on different parts of the networ k. These may warrant an amended order of priority. The type of local factors involved may includ e, for example, the presence of expansive clay subgrades, which are likely to cause maintenance probl ems, or the combination of steep slopes and high rainfall where run-off may accelerate the process of erosion. The maintenance engineer should feel free to reorder the list of priorities to suit loca l conditions, where necessary. Alternative prioritisation methods 7 . 3 5 Box 7.3 provides some notes on alternative methods that can be used to p rioritise maintenance works. Table 7.6 Example matrix of maintenance priorities Hierarchy of Traffic hierarchy maintenance activity 1 2 3 4 5 6 7 8 1. Emergency 1 7 8 9 10 11 12 13 2. Routine drainage 2 14 15 16 17 18 19 20 3. Routine pavement 3 21 24 27 30 33 36 39 4. Periodic 4 22 25 28 31 34 37 40 5. Other routine 5 23 26 29 32 33 34 35 6. Renewal 6 42 43 44 45 46 47 48 47 TRL Overseas Road Note 1, 3rd edition Box 7.3 Alternative prioritisation methods An alternative method of prioritisation can be used that takes into acco unt the cost-effectiveness. In this context, ‘effectiveness’ is the measure of the future ‘worth’ of the works that are undertaken. ‘Cost’ is the present-day cost of the works. Cost-effectiveness is, simply, the ratio of effectiveness to cost. The ratio can be used in the relative comparison of options. Future consequences of actions are only taken int o account through the inclusion of the expected life of the treatment. Thus: Simple cost-effectiveness methods tend to give priority to the cheaper t reatments, such as surface dressing, because these give good returns in terms of increased life per unit of c ost, but the methods do not take account of consequential costs. Because of the impact of mobilisation costs, the size of works also affects the cost- effectiveness. If computers are available, then more sophisticated prioritisation can a lso be used. These are described in Road maintenance management: concepts and systems (Robinson and others 1998). Expected life in years of the treatment alternative Cost-effectiveness = Unit cost Determining the work programme 7 . 3 6 The next step is to compare the costs of the proposed maintenance and re newal works with the funds available. Budgeting procedures within the road administration may mean that the funds available for routine, periodic and renewal works are not interchangeabl e. If this is the case, then priorities need to be assigned separately for works to be undertaken wit hin each budget head. There may also be a need, from an equity point of view, to assign at least a m inimum budget level to each sub-district covered by the road administration. This also needs to be t aken into account in the prioritisation. 7 . 3 7 The extent to which the maintenance engineer can influence how the avail able budget is spent will depend on the resource allocation procedures in his organisat ion. Some road administrations may allocate specific amounts of labour, equipment and m aterials whose costs are charged for the whole year regardless of use. Others may only define a t otal budget and leave the maintenance engineer free to purchase materials and hire whatever labour and equipment are needed. In most cases, the procedures will fall somewhere between these extremes. 7 . 3 8 A convenient method of developing the prioritised works programme is to produce a paper form for each maintenance activity that is needed. The form can contain a summary of the resource requirements and estimated costs for the activity. The forms should all be placed in a ring binder, initially following the order of priority defined in the master list, wi th the top priority tasks at the front and the lowest priority tasks at the end. The order of the forms i n the file can be changed where necessary to take account of local conditions, as described above. By working through the file, the maintenance engineer can calculate how far the available resou rces will extend. It is therefore possible to identify which activities can be included in the p rogramme for the year, and which tasks must be deferred until at least the next financial year. Som e flexibility and adjustment of priorities may be necessary to make sure that all the funds available are used. As noted above, programming must be carried out separately for each budget head. 7 . 3 9 If computer-based spreadsheets are available, then these can provide a v ery convenient mechanism for carrying out the programming activity. 7 . 4 0 Where funds are particularly short, it may only be possible to undertake a small fraction of the required works. The temptation to spread available funds thinly over the whole network should be avoided in this case, since this will lead to the whole network becom ing unserviceable over time. It is better to identify a ‘core network’ of strategic and e conomic importance and to focus the funding on these roads only. This will at least ensure that part of the network remains serviceable, and will reduce future rehabilitation needs. Identification of a core ne twork needs to be covered in the road maintenance policy (see Chapter 2). However, admitting the ne ed for a core network can be politically contentious. 48TRL Overseas Road Note 1, 3rd edition 7 . 4 1 The works programme produced in this way needs to be presented in the fo rmat necessary for submission for budget approval. Normally, the budget awarded will be insufficient to fund all of the works identified. Depending on the budgeting process, the budget awa rded may identify the specific works to be funded, or may only award a sum of money for undert aking a variety of activities. In the latter case, the prioritised work programme can be us ed to define those works that are to be undertaken from the budget. The list of funded works becomes t he ‘commitment’ for the coming year. 49 TRL Overseas Road Note 1, 3rd edition 8 Preparation and operations management 8 . 1 Preparation and operations management have the following components:  Preparation: – works design; – procurement by contract.  Operations management:– contract supervision; – day-to-day management of works carried out by in-house teams. Works design 8 . 2 Whereas formal designs are needed for periodic and renewal works, most r outine works do not need designing. Design methods are beyond the scope of this Note, bu t reference should be made to the methods indicated in Table 8.1 for activities. Table 8.1 Maintenance and renewal design methods Activity Design method Routine Patching, crack sealing and local sealing (asphalt). Overseas Road Note 2 (TRRL1985). Patching, crack sealing and joint repair (concrete). Concrete pavement maintenance manual (Highways Agency and Britpave 2001). Periodic Fog and slurry seal (asphalt). Overseas Road Note 3 (TRL 2000), TRH3 (COLTO 1998). Otta seal. NPRA Publication No 93 (Norwegian Public Roads Association 1999). Surface dressing (asphalt). Overseas Road Note 2 or 3 (TRRL 1985, TRL 2000). Thin overlay (asphalt). Overseas Road Note 19 (TRL 2002). Regravelling (unpaved). Overseas Road Note 2 (TRRL 1985). Renewal Overlay (asphalt). Overseas Road Note 18 and 19 (TRL 1999, 2002). Pavement reconstruction (asphalt). Overseas Road Note 31 (TRL 1993). Slab replacement (concrete). Concrete pavement maintenance manual (Highways Agency and Britpave 2001). Procurement by contract Forms of contract 8 . 3 Civil engineering contracts for maintenance and renewal works procuremen t can be categorised depending on the payment mechanisms used:  Unit rate.  Lump sum.  Cost-plus.  Target price. The main features of contracts based on these payment types are describe d below. 50TRL Overseas Road Note 1, 3rd edition 8 . 4 In unit rate contracts, the works are broken down under a number of quan tified items and listed in a bill of quantities. Prior to works execution, tenderers are requested to quote a unit rate for each of these items. The maintenance engineer will normally accept the l owest tender, and the unit rate becomes the basis for payment by measuring the work done under each item. The final cost of a unit rate contract can end up being considerably higher than the tende r. 8 . 5 In lump sum contracts, the contractor is paid a fixed price for completi ng all works. A difficulty with this contract form is that the contractor’s responsib ility is assumed to include all work considered incidental to the completion of the contract, whether or not they are included in the contract documents. An experienced contractor should be able to fore see the need for incidental items and allow for their inclusion in the tender. However, problems can occur when the lump sum is deemed to cover risks that may substantially change the scope of the work to be carried out. High tender prices can result. Lump sum contracts can result in disputes on interpretation of the contract documents, other than for very simple and straightforward works . 8 . 6 In cost-plus types of contract, the contractor is paid the direct costs of personnel, machines and materials based on accounting records. The only competitive element is for tenderers to quote a percentage mark-up on the direct costs, or a fixed sum, to cover overhea ds and profit. Such an arrangement involves virtually no risks to the contractor, and guarantee s a fixed income. However, it provides no incentives to carry out works in an efficient manner: the longer the work takes, the greater will be the payments made. Cost-plus contracts should only be us ed for works that are complex, and where quantities are difficult to assess in advance, such a s bridge repairs. 8 . 7 Target price contracts add incentives of economy to the cost-plus arrang ements. A preliminary cost is estimated and, on completion, the difference between this target and the actual cost is taken into account by calculating a positive or negative adjustm ent to the mark-up (or fixed sum) according to a pre-agreed formula. The target price approach can s uffer from a lack of clarity about how awards and penalties are related to the contractor’s perfor mance. Unforeseen risks can cause the contractor to incur losses. Although target price contracts of fer some advantages, a relatively sophisticated contracting environment is needed for them to b e effective. In the absence of this, unit rate or lump sum contracts should normally be used. Specifications 8 . 8 There are two basic types of specifications that can be used in maintena nce and renewal contracts:  ‘Procedural’ (or ‘method’) specification, where the employ er defines details of the work to be carried out (sometimes known colloquially as a ‘cook-book’ specif ication).  ‘Functional’ (or ‘end-product’) specification, where the e mployer defines the result to be achieved by the work in terms of a functional or performance requirement . 8 . 9 Procedural specifications have been used traditionally for roads works. They are relatively easy to specify and to measure. They have relatively high supervisory re quirements, particularly for maintenance works. 8 . 1 0 Functional specifications are, in principle, attractive for road mainten ance works contracts. However, they require a fundamentally different way of working to conven tional contracts. Contractual performance is defined in functional terms, such as required maximum depth of rutting, maximum height of grass on the verge, etc. Contractors can then determin e the most appropriate way to meet the performance requirement that maximises the use of their own particular skills, equipment and use of materials. Supervision requirements are therefore m inimised, since it is only necessary to test the end result on a sample basis. The main difficulty with functional specifications is the need to describe and define the functional requirements for all a ctivities. Although this approach can be used in ‘lengthworker contracts’ (see below), it s more general use is only recommended where there is considerable experience of contracting and a mature contract market. 8 . 1 1 A particular form of functional specification is used in ‘lengthworke r contracts’, which can be effective for the routine maintenance of low-volume unpaved roads. ‘ Lengthworkers’ are employed, on a contract basis, to carry out routine maintenance activiti es on specific sections of road, typically 1.5-2.0km in length. Work is undertaken on the basis nor mally of a simple contract 51 TRL Overseas Road Note 1, 3rd edition letter. Hand tools and a wheelbarrow may need to be provided. The contra ctor is expected to live close to the road, so that transport is not needed, and to work part-tim e on the road (typically 12 days per month). Activities include clearing ditches and vegetation, an d repairing pot-holes. The work is typically inspected once-a-month to ensure that road conditions are satisfactory, and to make payments. If road conditions do not meet contractual targets, then payments can be reduced. Persistent poor performance can result in the contractor being replaced. Contract procedures 8 . 1 2 Contracts are generally complex legal documents, so standard contract do cuments are normally used. The most widely recognised forms of standard contracts are produced by the Fédération Internationale des Ingénieurs-Conseils (FIDIC) and the UK Instituti on of Civil Engineers (ICE):  FIDIC conditions of contract for construction, for traditional contracts where the employer prepares the design (FIDIC 1999a).  FIDIC short form of contract, for small and simple contracts (FIDIC 199 9b).  ICE standard conditions of contract (Institution of Civil Engineers 199 6). General advice on contracting out road maintenance activities is given b y the World Bank (Lantran 1990-1993). 8 . 1 3 For contracts awarded to the private sector, a select list of tenderers should be maintained on the basis of type of work and range of value. Such lists should be compi led by vetting financial performance and previous experience of respondents to public advertiseme nts. Standard tendering procedures should be adopted, and the following general principles adher ed to:  Non-commercial matters should not be considered when drawing up select l ists; bias is to be avoided.  Contractors on the select list should be those able to provide the least expensive tenders while competent to undertake work to the satisfaction of the client.  All contractors on the select list should be given the opportunity to te nder from time-to-time.  The number of contractors invited to tender should be between four and s ix; sufficient numbers for competition, but not so excessive as to waste effort and increase th e level of contractor tendering costs unnecessarily.  Tenders should be received at a time and place notified in the tender in vitation, opened in the presence of authorised representatives, recorded and evaluated in an unb iased way.  The road administration should not be bound to accept the lowest tender, if there are good reasons to expect that a better result would be obtained by accepting a more expensive tender.  Details of tenders should be made public, but commercial confidences sho uld not be unreasonably disclosed. 8 . 1 4 The following general principles apply to the effective management of co ntracts:  Avoid unnecessary complex documentation.  Standardise contract procedures as far as possible.  Contracts should enable standards and specifications to be enforceable i n a clear and unambiguous manner.  The quality of work can be improved through the use of functional (end- product) specifications, but these can be difficult to set up to be effective.  The size and scope of contract should aim to make the most efficient use of available resources, and spread fixed costs in an optimal way. 52TRL Overseas Road Note 1, 3rd edition 8.15 A key objective of works supervision is to achieve good quality work wit hin programme and to budget, in accordance with the specification, drawings and other contract documents. The way in which work is performed is entirely the responsibility of the con tractor, unless it conflicts with the contract documents or legislation. The client organisation shou ld endeavour to provide supervisory staff resources with adequate relevant experience and traini ng, together with testing and other back-up facilities to enable a satisfactory level of quality c ontrol to be achieved. External consultants should be used for this when there are insufficient skilled staff in-house. Factors which affect the desirable level of supervision include:  Scale and type of work.  Duration.  Capability of contractor.  Complexity of work.  Type of contract and associated procedures.  Third party liaison and safety requirements.  Implications of defective work going unnoticed.  Degree of definition provided by contract documents. It is vital that the maintenance engineer ensures that all contracts are properly supervised, and that all specifications are met before payments are authorised. More detailed advice on contract supervision is given in Road engineering for development (Robinson and Thagesen 2004). 8 . 1 6 Standardised sampling procedures should be adopted that are in accordanc e with national standard documents, where applicable. The frequency of sampling should r eflect variability in materials quality and the quality of materials production, mixing, trans port and site procedures. Normally, sampling frequency will be prescribed in the specification, bu t may need to be modified to suit individual circumstances. Resources available for sampling and t esting requirements should be in balance with the frequency of tests required, and take into accoun t the speed of work necessary to avoid delay to subsequent operations. 8 . 1 7 Contractors should be notified immediately of work or materials not meet ing specifications. Careful consideration should be given to the reasons for non-compliance before taking action. Possible actions include re-working the material, removing the material, reducing payment or obtaining a performance guarantee bond from the contractor. Operations management of in-house works 8 . 1 8 Once a committed work programme is available, the maintenance engineer n eeds to convert this into a work schedule that indicates how the work will be timed thro ughout the year. This is, essentially, a project management exercise. Use should be made of bar ch arts and resource diagrams to schedule when work is best undertaken and to balance the use of resources to ensure their high utilisation. If a computer is available, a standard project m anagement software package can be used to assist with this process. Activities to be undertaken in the near future should be scheduled more accurately than those to be undertaken in future months. Schedules should then be firmed-up as time progresses. Scheduling needs to take into account the following aspects relating to activities:  Timing – some activities must be carried out at particular times in the year ; for example, grass grows more rapidly during the rainy season, and should therefore be cut at the end of this season; drains should be cleared before the rainy season starts.  Frequency – some activities are required at regular intervals; for example, a g ravel road may require regular grading or dragging of its surface to inhibit traffic-in duced corrugations.  Dependency – some activities can only be carried out once others have been compl eted; for example, surface dressing should be carried out only after any pot-holes have been patched. 53 TRL Overseas Road Note 1, 3rd edition 8 . 1 9 In scheduling the work, the maintenance engineer should take account of the delivery periods for materials. If deliveries are likely to be uncertain, it is a dvisable to stockpile basic materials, such as aggregates, cement and bitumen. These will need to be stored securely and kept in good condition. 8 . 2 0 It is important to have sufficient basic equipment and tools to meet day -to-day requirements. The maintenance engineer will probably not be responsible for the supply of plant and vehicles, since this is usually handled separately within the organisation. Shorta ge of working equipment or vehicles is almost always a major symptom of inefficiency in maintenance organisations. The maintenance engineer should, therefore, be aware of the supply situation and ensure that equipment is systematically maintained in good working order. It is particularly h elpful to establish a daily routine of equipment maintenance. This can be done through the following measures carried out by the maintenance engineer:  Ensuring that operators appreciate the purpose and benefits of preventat ive maintenance, understand the maintenance needs of the equipment they use, and are trai ned to look after this equipment on a daily basis.  Arrange for a regular supply of oil and grease, etc, to be made availabl e; this supply will need secure storage facilities under the supervision of a storeman.  Checking personally that the daily maintenance routine is being carried out, and demonstrating personal concern for equipment maintenance standards.  Using site visits to observe how operators treat their equipment and dis couraging its mishandling or misuse. Guidance on equipment management is beyond the scope of this Note, but f urther information is given by the World Bank (Lantran 1990-1993). 8 . 2 1 The maintenance engineer should prepare detailed work instructions for t he teams under his direction, based on near-term activities included in the schedule. These are essentially sets of instructions that tell the foremen or technicians, supervising an activi ty, how much work is to be done each day, the time it should take, and the labour, equipment and ma terials to be used. Work instructions should cover periods of not less than two weeks and not mor e than four weeks. Shorter periods probably do not warrant the effort of preparing a work instructi on, while longer periods risk losing a sense of urgency. 8 . 2 2 In drawing up work instructions, the maintenance engineer should first d iscuss the work with the foremen and supervisors who will have to manage the activity. It is essential for these personnel to feel confident that the ‘production target’ – the output of work required each day – is pitched at a realistic level. One useful idea is to ask the foremen to draft their ow n work instructions. The maintenance engineer can use these as a basis for discussion and agreeme nt. The results are helpful in developing the work instructions that are issued to teams. 8 . 2 3 Figure 8.1 shows an example of a completed work instruction. Normally, t wo or more of these would be issued to cover the schedule period. The work instruction provides information on work to be carried out, resources to be used and targets to be achieved. It also provides a daily record of the progress made on a job to allow the actual output of work to be measured against the target output. The target is the first item to be recorded on the work i nstruction; the amounts of each resource to be used are entered next, in the top half of each line. The work instruction is then issued to the supervisor who enters, in the bottom half of each line, the progr ess actually made and the resources used day-by-day. At the end of the schedule period, the superv isor returns the completed forms to the maintenance engineer who calculates, in percentage terms, h ow much of the production target has been achieved and so is able to assess the product ivity of the work. Any significant shortfalls that may occur, or instances of high achievement, can be discussed with the supervisory personnel when the next schedule is being prepared. 8 . 2 4 Technical aspects of the execution of maintenance activities at district level are the subject of Overseas Road Note 2 (TRRL 1985). The organisation of work on site needs some consideratio n, particularly if large-scale in-house works are involved. Health and safe ty issues must be given due consideration, and work should be undertaken to meet any environmental l egislative requirements. 54TRL Overseas Road Note 1, 3rd edition Figure 8.1 Example of work instruction form District: Period: Section: Sub -section: Length: Width: metres metres Work instruction Team members: Target production Unit M T W T F S S Total % Resources Si gned……………………………………………… .. Activity: Th. E. Engineer Central 5-18 October 2003 A0102 6.5 225 2 Regravelling H Smith C Jones S Done Gravel (Subcontract) Grader Roller (2) 0.5km/day km m 3 hr hr 350m 3/day 8/day 16/day 300 300 100 100 400 0 400 1600 3.500 2.490 71 2450 65 688 8 b/d842 56 75 16 16 7 8 16 -16 79 112 70 4 55 TRL Overseas Road Note 1, 3rd edition In particular, labour-based methods will require careful organisation an d management. Labour has to be available in sufficient numbers in the right place and at the righ t time, so arrangements may need to be made for transporting the labour force to and from work sites . Standardised, good- quality tools and equipment will be needed to achieve high levels of out put. Attention should also be paid to the health and nutrition of the workers. In addition to the h umanitarian aspect, this also helps to increase productivity. 8 . 2 5 Works performed in-house should generally be subject to the same level o f supervision as that applied to external contractors. 8 . 2 6 The maintenance engineers must ensure that the contractor uses safe work ing practices on site. It may be helpful for the road engineer to explain to the contract or the impact that an accident will have on both the worker and their family. A schedule of penalties f or non-compliance can be included in a contract. Site safety is often covered by national regulat ions but, in the absence of these, general safety issues are presented in Box 8.1. 56TRL Overseas Road Note 1, 3rd edition Box 8.1 Site safety measures General operations Many labourers may be unfamiliar with site practices and equipment. Prov ide training for recruited labour on the dangers of site work, precautions (how to avoid danger) and protec tion (how to protect against harm). Driving Many site accidents relate to driving. Ensure that only competent driver s work on the site. Warn and then dismiss drivers who drive poorly. Do not permit any driving under the in fluence of alcohol or drugs. First aid All sites must have first aid facilities staffed by a trained health wor ker. Access to a nearby clinic must be possible at all times in case of more serious injury. For very small sit es or mobile operations, at least one person in the team should have basic first aid training and carry a first aid k it. Manual excavation A group of labourers working closely together can put each other at risk of injury. Instruct a supervisor to ensure that labourers are well spread out along a gravel quarry face or a drain excavation line. Gravel pit excavation Vertical gravel faces can collapse and trap labourers. Excavate a maximu m vertical face of one metre, with a horizontal step of at least two metres to the next face to reduce this r isk. Tractor operations Only drivers may sit on a moving tractor. No one should sit on mudguards or other parts of a tractor. All passengers should sit within, and not on the sides of, a towed trailer. Equipment operations Instruct a worker to accompany all motorised plant to ensure that labour ers are aware of its movements, particularly when reversing. Motorised plant should carry no passengers. Clothing Activities such as concrete and asphalt work require specialised protect ive clothing. This can include gloves, boots, overalls, goggles, dust masks and face masks. Hot bitumen will re quire heat resistant clothing. Explain clearly the dangers of working with these materials. Ensure that the pro tective clothing is worn. Provide an adequate supply of cleaning materials. Rock breaking Issue all workers who produce chippings or aggregate with goggles and gl oves. Ensure that the protective equipment is worn. Tree felling Trees can fall in unexpected directions. Maintain a clear area of radius greater than the height of the tree. One worker should announce when the tree is ready to fall. Traffic management Place warning signs in front of and behind each work gang at a sufficien t distance to enable vehicles to slow down and stop. One worker with a flag should be present at each end of the works to warn drivers of the activities ahead. If the road is blocked, make a detour available at all times. See Overseas Road Note 2 (TRRL 1985), or national guidance, for recommended sign layouts. Lengthworkers Lengthworkers are vulnerable to traffic accidents when working alone. Th e lengthworker should place warning signs along the road in both directions before starting work. Public safety Roads are public places. Ensure that members of the public are protected from site activities. Provide pedestrian detours, if necessary. When closing gravel pits, batter back all vertica l faces. Instruct equipment operators to drive slowly, especially on small access roads with poor visibility. Pro tect culvert excavations with barriers. A contractor may be legally required to provide third-party insurance agai nst injury to people and damage to property when on site. 57 TRL Overseas Road Note 1, 3rd edition 9 Monitoring and audit 9 . 1 Monitoring and audit represent the final step in the management cycle for undertaking an activity. Both should be carried out to review each of the network manag ement activities of programming, preparation and operations management. ‘Monitoring’ p rovides feedback to the management process, whereas ‘audit’ provides a check on how a part icular activity has been carried out. 9 . 2 The audit function is, essentially, a physical integrity check to ensure that:  Work has actually been undertaken, where specified, to any pre-defined s tandards, specifications or procedures – this is known as ‘technical audit’ .  Funds have been spent for the purposes actually intended, and that costs and other resources have been accounted for properly – this is known as ‘financial aud it’. Auditing is normally done on a sample basis by a special unit, which is independent of the main functional branches of the road administration. The three key areas over which control needs to be exercised are:  Quality of work.  Final cost of work.  Duration of work. 9 . 3 Monitoring enables management to learn from past experience. For example , aims can be redefined to reflect the actual achievements; cost assumptions can be re vised to reflect those actually achieved in practice; procedures, technical methods and specifi cations may be improved as a result of monitoring. Thus, monitoring enables the maintenance enginee r to check the quality and effectiveness of the work being done. It provides data that can be used to improve the management and performance of future maintenance operations. Questions asked should include:  Are the objectives and desired levels of service being achieved?  Are the works being completed satisfactorily?  Is value-for-money being obtained? 9 . 4 Key objectives from the road maintenance policy framework should be sele cted as performance indicators. These can be made public to give confidence to t hose using the road network that its management is effective and efficient. The same perform ance indicators should be used irrespective of whether works are carried out by an in-house unit o r under contract. Some indicators of effectiveness and value-for-money are given in Box 9.1. Box 9.1 Examples of performance indicators Indicators of effectiveness  Volume of the various works carried out against that planned for each ac tivity  Trends relating to changes in network condition  Expenditures per kilometre on different road classes for different treat ment types  Value and proportion of maintenance carried out on a year-by-year basis  Cumulative amount of network treated or upgraded Indicators of value-for-money  Out-turn unit costs of works undertaken  Time and cost over-runs 58TRL Overseas Road Note 1, 3rd edition 9.5 Monitoring involves:  Site visits.  Desk review. Site visits are an important part of monitoring. Because of the length o f road to be covered, site visits will require the use of a vehicle, which should be driven slowly along the section being examined. Enough time should be allowed for the maintenance engineer to make a series of detailed inspections on foot. It is therefore best if the engineer trave ls as a passenger to concentrate on the inspection, with a driver being responsible for the progress and safety of the vehicle. The road surface, side drains, culverts and soils all need to be examined. 9 . 6 Desk review is an office task that involves reviewing all the maintenanc e documentation, i.e. inspection reports, completed worksheets, etc. It provides the opportuni ty to assess the performance of the maintenance programme and the effectiveness of the management sys tem. It provides an opportunity to check that adequate resources were allocated to each task and that maintenance problems were treated efficiently; cost estimates can be compared with e xpenditure and production targets with output; and the reasons for inconsistencies or shortfalls c an be identified. In some cases, resources may have been insufficient; in others, targets may have been pitched too high. 9 . 7 The maintenance engineer should discuss the results of the desk review w ith supervisors and try to find ways of remedying any deficiencies. It is likely that some o f these may result from factors beyond the control of the maintenance staff, but it should be po ssible to identify those points that can be put right and to plan appropriately for the following year. 59 TRL Overseas Road Note 1, 3rd edition 10 Information systems 1 0 . 1 Computerised information and management systems can be used to assist wi th most aspects of the road maintenance management process. The need to collect, store a nd utilise significant amounts of information about the road network makes a computer-based app roach very attractive. Many proprietary systems are available. Detailed guidance on the design, selection and operation of road management systems is provided in Overseas Road Note 15 (TRL 1998). It is crucial that a systematic approach is used for selecting and implementing systems. A su mmary of the recommendations in this area are given in Box 10.1. 1 0 . 2 Past experience suggests that the following are key issues that must be met when implementing systems to support the maintenance management process:  The system must be adapted to suit the local conditions.  Existing methods and procedures that cannot be used unchanged should be modified rather than replaced with new ones.  Sufficient, well trained and motivated staff must be provided.  The introduction of the system must be properly supervised. Box 10.1 Steps in the system selection process 1 Commitment phase (decide to proceed)  Obtain commitment from key individuals in the road administration to the system implementation process. 2 Requirements phase (decide what is wanted)  Agree the objective for the system and determine what components the sys tem needs to contain; decisions should be supported by cost-benefit analysis. 3 Specification phase (decide what is needed)  Identify users of the system and the outputs that they will require to s upport them in their management decision-making.  Identify data needs and models required to produce these outputs. 4 Procurement phase (choose the best solution)  Identify appropriate software, together with hardware and operating syst em requirements necessary to support it. 5 Operations phase (make the system work)  Implement the chosen system.  Provide initial and on-going training.  Manage operation of the system. 60TRL Overseas Road Note 1, 3rd edition References Committee of Land Transport Officials (COLTO) (1998) . Technical recommendations for highways: surfacing seals for rural and urban roads . Draft TRH3. Pretoria: Committee of Land Transport Officials. Fédération Internationale des Ingénieurs-Conseils (FIDIC) (1 999a) . Conditions of contract for construction . Lausanne: Fédération Internationale des Ingénieurs-Conseils. Fédération Internationale des Ingénieurs-Conseils (FIDIC) (1 999b). Short form of contract. Lausanne: Fédération Internationale des Ingénieurs-Conseils. Highways Agency and Britpave (2001). Concrete pavement maintenance manual. Crowthorne: The Concrete Society. Institution of Highways and Transportation (IHT) (1990) . Highway safety guidelines: accident reduction and prevention, international edition . London: Institution of Highways and Transportation. Institution of Civil Engineers (1996) . The engineering and construction contract . London: Thomas Telford, 2nd edition. Lantran J M (1990-1993). Contracting out road maintenance activities. Volumes I-IV. Sub-Saharan Africa Transport Policy Program, Road Maintenance Initiative . Washington DC: The World Bank. Norwegian Public Roads Association (1999) . A guide to the use of otta seals . Road Technology Department, International Division, Publication No 93. Oslo: Directorate of Public Roads. PIARC (1999) . HDM-4: highway development and management tool . The Highway Development and Management Series. Paris: PIARC World Road Association. Robinson R, Danielson U and Snaith M (1998) . Road maintenance management: concepts and systems . Basingstoke: Macmillan Press. Robinson R and Thagesen B (2004) . Road engineering for development . (In preparation) . Transport Research Laboratory (TRL) (1991) . Towards safer roads in developing countries: a guide for planners and engineers . Crowthorne: TRL Limited. Transport Research Laboratory (TRL) (1993) . A guide to the structural design of bitumen-surfaced roads in tropical and sub-tropical countries . Overseas Road Note 31. Crowthorne: TRL Limited. Transport Research Laboratory (TRL) (1998) . Guidelines for the design and operation of road management systems . Overseas Road Note 15. Crowthorne: TRL Limited. Transport Research Laboratory (TRL) (1999). A guide to pavement evaluation and maintenance of bitumen-surfaced roads in tropical and sub-tropical countries . Overseas Road Note 18. Crowthorne: TRL Limited. Transport Research Laboratory (TRL) (2000) . A guide to surface dressing in tropical and sub- tropical countries . Overseas Road Note 3 (2nd edition). Crowthorne: TRL Limited. Transport Research Laboratory (TRL) (2002). A guide to the design of hot mix asphalt in tropical and sub-tropical countries . Overseas Road Note 19. Crowthorne: TRL Limited. Transport Research Laboratory (TRL) (2003) . A guide to the measurement of axle loads in developing countries using a portable weighbridge . Overseas Road Note 40. Crowthorne: TRL Limited. 61 TRL Overseas Road Note 1, 3rd edition Transport and Road Research Laboratory (TRRL) (1985) . Maintenance techniques for district engineers . Overseas Road Note 2 (2nd edition). Crowthorne: TRL Limited. Transport and Road Research Laboratory (TRRL) (1988) . A guide to bridge inspection and data systems for district engineers, Volumes 1 and 2. Overseas Road Note 7. Crowthorne: TRL Limited. 62TRL Overseas Road Note 1, 3rd edition Appendix A: Glossary Activity Any work or intervention that is carried out on the road network, including works to undertake road maintenance, new construction, improvements, and the like. Audit A physical check, usually on a sample basis, that work has been carried out, where specified, to pre-defined standards or procedures, and that costs and other resources have been accounted for properly. Budget head A category under which a budget is broken down for the purposes of its allocation. Capital budget The government budget normally used to fund major projects. Carriageway That part of the road used by traffic. Chainage Distance measured along the road from a defined datum. Client The body commissioning works or services. Committed works Works for which a budget has been approved. Condition-responsive Works that are carried out in response to defects exceeding a defined treatment threshold. Construction ‘Development works’. Contract An agreement between two willing parties to perform some action, where there has been an ‘offer’, an ‘acceptance’ and a ‘c onsideration’ (usually money). Contractor The supplier of works or services under a contract. Contractual claim A request made by a contractor for additional payment or an extension of time necessary to undertake works that are unforeseen or not specified in the contract. Core road network That part of the road network, normally of a strategic nature, that will always be maintained even when available resources are extremely limited. Cost-plus contract Works contract where the contractor is paid for monies actually spent plus a mark-up for overheads and profit. Customer The beneficiary of a service being provided. The main customers for a road administration are the road users, who include: owners and operators of commercial vehicles and buses; representatives of industry, commerce and agriculture, who have a vested interest in an efficient road network to support their business operations; and the travelling public using the road network. Cyclic works Routine maintenance works carried out each year whose frequency depends on environment and not traffic. Data Facts (quantities, values, names, etc) from which other information ma y be inferred. Defect Deteriorated from new condition. Designated road A road that is a legal entity under a Roads Act or similar legislation ( the terms ‘adopted’, ‘declared’, ‘gazetted’, ‘proclaime d’ are used in some countries). Development works Works which extend the capacity of the network by widening, realignment or constructing a new section. Direct labour ‘In-house works implementation’. Emergency works Works carried out on the network to reopen a cut or blocked road. 63 TRL Overseas Road Note 1, 3rd edition Equipment-based works Works that are undertaken mainly with the assistance of mechanical equipment. Gazetteer A list of designated links or sections that defines the road network. Feature A fundamental component of the road, such as the carriageway, shoulder, footway, etc. Force account ‘In-house works implementation’. Functional specification A specification that is defined in terms of the end-result to be achieve d. In-house works Works undertaken by a unit of the client’s own organisation. implementation Information Data that has been transformed to be meaningful through processing and dissemination. Intervention level The threshold above or below which action must be taken to ensure that standards are met, often expressed in terms of defined thresholds of road condition, response time, or performance. Inventory The physical attributes of the road or other asset being managed. Labour-based works Works that are undertaken mainly by manual labour with the assistance only of tools and small items of mechanical equipment. Lengthworker An individual responsible for carrying out maintenance works on a defined length of road. Level of service A subjective measure of user requirements. Link A length of road where traffic volumes are reasonably uniform . Lump sum contract Works contract where the contractor is paid a pre-agreed fixed sum for all works carried out. Maintenance The group of works that enables a road to continue to provide an acceptable level of service. Maintenance reduces road deterioration, lowers road user costs, and keeps the road open on a continuous basis. Management The planned and organised use of resources to achieve particular goals or objectives. Management cycle A series of well-defined steps which take the management process through the decision making tasks. Typical steps would be i) define aims; ii) assess needs; iii) determine options; iv) choose actions; v ) implement activities; vi) monitor and audit. The process typically completes the cycle once in each periodic cycle of the particular management function. Management system A set of procedures to assist with management. Marker post A fixed item at the roadside to indicate location. Mission (statement) This outlines, in broad terms, the nature of the operation being managed by the organisation responsible for the road network. Monitoring Reviewing past activities to learn from experience to enable better objectives to be set in the future. Moving observer count Method of determining traffic flow whilst driving along a length of road . Network A particular grouping of roads for management purposes; examples are the national road network; trunk road network; paved road network, etc. Network management The process of managing a road network, including the activities of ‘strategic planning’, ‘programming’, ‘preparation’ and ‘operations management’. Network referencing The process of breaking the road network down into successively smaller links, segments and sections, each of which can be defined uniquely for road management purposes. 64TRL Overseas Road Note 1, 3rd edition Network screening Preliminary determination of which road sections are likely to need treatment. Node The start and end point of a road section. Objective A specific and measurable goal or target to be achieved by a body within the short to medium term (tactical) or long term (strategic) time scale. Operation(s) The on-going activities of an organisation, decisions on the management of which are made on a near-term basis, typically daily or weekly, including the scheduling of work to be carried out, monitoring in terms of labour, equipment and materials, the recording of work completed, and the use of this information for monitoring and control. Operational cost A fundamental cost-estimating technique that compiles the total cost of the work from consideration of the constituent operations or activities revealed by the method statement and programme, and from the accumulated demand for resources. Overlay works The addition of material on top of a pavement for the purpose of increasing its structural strength. Performance bond An unconditional bank guarantee, in favour of the client, that a contractor will meet all contractual requirements. Performance indicator A sub-set of objectives, performance against which is published for public scrutiny. Performance standard This specifies the resource requirements for each activity to be carried out, and builds up a consistent description of the activity based on a preferred and specified method of working, and resources of equipment, labour and materials to perform the activity in accordance with the preferred method. Periodic works Works carried out on the network planned at discrete intervals in time o f several years. Planning (strategic) This involves an analysis of the road system as a whole, typically requiring the preparation of long term, or strategic, estimates of expenditure for road development and conservation under various budgetary and economic scenarios; predictions may be made of expenditure under selected budget heads, and forecasts of road conditions, in terms of key indicators, under a variety of funding level s. Policy The statement or series of statements which define the basic rules and requirements which can guide all decisions and actions that need to be taken. Policy framework A hierarchical set of statements that define policy relevant to differen t bodies or levels of administration; typically consisting of mission statement, objectives and standards that define in detail the aims of an organisation and how it proposes to achieve these. Preparation The near-term planning stage where road schemes and projects are packaged for implementation. At this stage, designs are refined and prepared in more detail; bills of quantities and detailed costings are made; together with work instructions and contracts; detailed specifications and costings are likely to be drawn up. Preventive works Periodic works on the network designed to prevent the rapid escalation of deterioration. Priority index A parameter whose numerical value indicates where in a list of prioritie s particular actions lie. Procedure A documented series of steps for carrying out a particular activity or task. 65 TRL Overseas Road Note 1, 3rd edition Procedural specification A specification that is defined in terms of the method to be followed. Programming The preparation, under budget constraints, of multi-year works and expenditure programmes in which those sections of the network likely to require treatment, and new construction possibilities, are identified and selected; a tactical planning exercise. Project A set of activities with a defined start and finish, and which consume resources in moving from start to finish. Quality control Checking completed works to ensure that specifications have been met. Rating A score assigned to indicate condition or priority. Reactive works Routine maintenance activities that are carried out each year whose extent depends on a combination of traffic and environmental effects. Reconstruction Works requiring the replacement of some of the existing infrastructure asset; e.g. pavement reconstruction requiring removal and replacement of road surfacing material. Recurrent budget The budget head often used to fund on-going activities and maintenance works. Rehabilitation Works that are needed to restore a road to a maintainable condition. Renewal Works to restore a road to a similar condition to when it was new. Resurfacing works The addition of material on top of a pavement for the purpose of reducing roughness or surface distress. Road administration The body responsible for managing the road network. Road class A grouping of road sections according to pre-defined rules, often based on issues of ownership, function, funding source, etc. Road management The process of maintaining and improving the existing road network to enable its continued use by traffic efficiently and safely, normally in a manner that is effective and environmentally sensitive; a process that i s attempting to optimise the overall performance of the road network over time. Roads board A committee set up to administer or to advise on the administration and management of a road network. Roads register A ‘gazetteer’. Roughness Longitudinal unevenness of the road surface that impacts on the suspension of vehicles. Routine works Works carried out on the network that are needed each year. Schedule A short to medium term plan for carrying out activities. Scheduled treatment Works that are carried out at pre-defined intervals of time. Section A length of road that is reasonably uniform in terms of its physical characteristics. Serviceability ‘Level of service’. Specification A detailed description of the attributes of the output from an activity, or of the steps by which that activity is carried out. Standard A detailed operational target to be achieved by an individual unit in an organisation to enable policy to be implemented; a requirement, sometimes legally enforceable, that a road administration is obliged to meet as part of its road management activity. Target price contract Works contract where the contractor is paid a fixed price plus an incentive payment for meeting pre-defined targets. Task A sub-division of an activity. 66TRL Overseas Road Note 1, 3rd edition Tender A formal written offer to carry out works, or to supply goods, material or services. Treatment Works to correct defects. Treatment length Contiguous lengths of road requiring common treatments. Treatment option One of a number of treatments that can be applied to correct the same defects. Unit rate A cost-estimating technique based on the traditional bill of quantity approach to pricing engineering work, typically relating to aggregate quantities of work to be carried out, measured in accordance with an appropriate method of measurement. Upgrading Works to increase the standard of a road; e.g. pavement strengthening, road widening. Utility Public service infrastructure; e.g. telecommunications, electricity, wat er. Visual inspection An inspection based on the use of simple measurements, or on subjective judgement. Work package A collection of works that are carried out under one contract or work instruction. Works All construction and maintenance activities that are carried out on the road network, normally sub-divided into routine maintenance, periodic maintenance, special works, rehabilitation, and development. Work order/instruction Written authorisation to carry out certain works. 67 TRL Overseas Road Note 1, 3rd edition Appendix B: Field survey procedures Survey types B.1 Three types of inspections are covered in this Note:  Inventory.  Network screening survey.  Visual inspection. The first section of the appendix deals with network screening surveys. The remainder of the appendix covers the procedures for visual inspections. Inventories and v isual inspections use largely the same field procedures. The recommendations for team organisa tion, safety, equipment and transport are common for the two types of surveys. The forms require d for inventory surveys will depend on the details of the network and item inventory to be recor ded. No specific examples are included here. Standard forms for recording the results of network s creening surveys and visual inspections are included in Appendix D. Network screening surveys B.2 The aim of network screening surveys is to identify the need for the mor e detailed visual inspections. B . 3 A network screening survey is carried out on the basis of road sections, rather than sub-sections. It is undertaken by an observer from a moving vehicle. This is a subject ive, cursory, inspection which assigns a ‘rating’ in the range of 5 (good) to 1 (poor), which relates to ‘serviceability’. Separate ratings are assigned to pavements, shoulders or footways, and t o side drainage. In the case of shoulders and footways, one value is assigned to represent the servic eability of all shoulders and footways in the section on both sides of the road. B.4 The maintenance engineer should develop an appropriate rating mechanism for local conditions. In the absence of this, or as a starting point, one of the f ollowing methods can be used. A simple rating method can be used for pavements by assigning a general rating, on a scale of 5 (excellent) to 1 (poor), to the general condition of each section. T he results can be used directly. The observer should also make a note of the likely remedial treatment ne eded on the section to guide the analysis of survey results. Any special problems should also b e noted. Complex rating of pavements A more detailed rating method can also be used to take into account spec ifically the riding quality and surface deterioration of the pavement. For each section, two ratings are made. The first relates to the perceived riding quality, and the second to the percentage length of the section that is defective. Appropriate ratings are given in Table B.1. The observer reco rds the characteristic riding quality of the section. In addition, the percentage length of the sectio n that has characteristic defectiveness should also be recorded. Figure B.1 shows an example of ho w these values can be entered on a survey form. The two ratings can be combined, as shown in T able B.2, and an overall rating can be read from the matrix. As above, the observer should make a note here of likely remedial treatment needed on the section and other relevant information. Table B.1 Pavement rating for riding quality and defectiveness Perceived riding quality of pavement Initial rating Smooth 5 Occasional slight unevenness 4 Continuous slight unevenness or occasional bump 3 Continuous unevenness 2 Continuous rough ride 1 Road impassable 0 68TRL Overseas Road Note 1, 3rd edition District:Date: Section Pavement Shoulder /Footway Signed…………………………………………… …..Inspector Drainage Network screening survey Indicative treatment/ notes Ride Defect A.N. Inspector A7011 Central 13 October 2003 A7012 A7013 A7014 A7015 B6951 B695248% 4 4 None 2 15% 2 2 Surface dress 3 15% 2 3 Surface dress 2 60% 2 3 Reconstruct pavement 48% 4 4 None 3 20% 2 3 None 3 15% 2 3 None Figure B1 Example of a completed network screening survey form for pavem ents 69 TRL Overseas Road Note 1, 3rd edition Table B.2 Combination of initial ratings to give a pavement rating Percentage length defective Perceived riding quality 0-5 6-10 11-20 21-50 51-100 5 Smooth 5 4 3 2 2 4 Occasional slight unevenness 4 4 3 2 2 3 Continuous slight unevenness or occasional bump 3 3 3 2 1 2 Continuous unevenness 2 3 3 2 1 1 Continuous rough ride 1 1 1 1 1 0 Road impassable 0 0 0 0 0 B.6 During the survey, the observer should also record a rating for shoulder s or footways, and for side drains, as illustrated in Figure B.1. As above, the maintenance eng ineer should develop an appropriate rating mechanism for local conditions but, in the absence of this, the values indicated in Table B.3 can be used. Table B.3 Rating for shoulders, footways and side drains Percentage length defective Rating 0-5 5 6-10 4 11-20 3 21-50 2 51-100 1 Visual inspection procedure B.7 The procedures given can apply to sections of a constant (fixed) lengt h or to variable-length sections. Surveys can be carried out of entire sections, or these can be broken down into sub-sections to provide shorter and more convenient road lengths for reporting purpose s. Typical sub-section lengths would be 100 to 200 metres. B.8 The aim of visual inspections is to record defects occurring in sections of road. The inspections are designed to be carried out by non-technical staff who ha ve been trained in the relevant survey techniques. As such, inspectors are not expected to make decisions about the cause of defects or to make other engineering judgements. It is envisaged that , for maintenance and renewal treatment-design purposes, a more detailed engineering inspectio n will be utilised in addition to the visual inspection, in which cores and other detailed sit e investigations will be carried out. These investigations are described in Overseas Road Note 18 (TRL 1999). B.9 Because visual inspection is a time-consuming process, it may only be po ssible, initially, to take representative measurements over perhaps one-tenth of the section o r sub-section length. As inspection teams become more skilled and as more teams are introduced, i t should become practicable to increase the coverage of the surveys until measurements a re taken over the entire section. Similarly, when the maintenance system is first introduced, it will probably only be possible for the inspector to assess the severity of defects by observat ion. As the system develops, physical measurement of defects should be gradually introduced into the inspection procedure; but the quality of visual assessments can be improved by having first-hand k nowledge of the physical measurement techniques. 70TRL Overseas Road Note 1, 3rd edition Table B.4 Equipment for inspections Item no Description 1 Transport. 2 Warning signs (‘men-at-work’). 3 High visibility safety jackets. 4 List of sections to be inspected and maps of the area. 5 Field survey procedures (this document). 6 Printed inspection forms. 7 Clip-boards. 8 Ballpoint pens or pencils. 9 Inspector’s notebook. 10 Measuring wheel or 30m measuring tape. 11 10m measuring tape or second measuring wheel. 12 Deformation gauge (two-metre straight-edge and calibrated wedge - see F igure B.2). 13 Road marking crayons or chalk. Visual inspection organisation Safety B.10Safety is a key aspect of the work. The road being inspected may have ve hicles travelling at high speed. Any person working on the road should, therefore, take simpl e and sensible precautions. Even when traffic is not heavy, safety procedures should no t be relaxed, since there may then be a danger from unexpected vehicles. B.11 All members of field survey teams, including drivers and any labourers, should wear high visibility safety jackets at all times during surveys. The transport veh icle should follow directly behind the survey team, and remain between the team and the traffic. The vehicle’s hazard warning lights should be switched on and, whenever possible, a ‘men-at-work’ sign should be attached to the vehicle, or placed behind it. B.12 W here possible, inspections on foot should be carried out while standing on the shoulder or footway. When measurements are being made on the carriageway by an inspe ctor, another team member should act as a lookout to warn of oncoming traffic. To minimise exposure to traffic, inspectors and team members should only step on to the carriageway when actually taking measurements. Particular care should be taken when measuring rut depth o n the far side of the road, since the transport vehicle will not be providing safety cover. B.13 Inspectors should report all road defects that affect road safety, even where there may be no specific requirement to do this in the survey being undertaken. Where pa per based inspections are used, notes can be recorded on the inspection form. If an unsafe situati on is observed, remedial action should be undertaken by the inspectors, wherever possible. For ex ample, if there is debris on the road, then this should be removed rather than reported. Examples of safety hazards to be reported are:  Traffic accidents.  Broken down vehicles on the road.  Landslide debris on the road or endangering the road.  Other debris. Equipment and transport B.14 Table B.4 sets out a check-list of the equipment required for the field work of inspections. 71 TRL Overseas Road Note 1, 3rd edition B.15 Transport is needed to carry teams to and from their place of work, to c arry equipment, and to give temporary shelter during bad weather. The vehicle provides safet y protection to the inspection team when working on the road. There is particular advantage if flashing roof-lights and ‘men-at-work’ warning signs can be attached to the vehicle for dis play when teams are working. The vehicle should display hazard warning lights when parked or moving s lowly on the road. Organisation and staffing of teams B.16 The basic duties of the team are the observation, measurement and record ing of defects. Composition of the team will depend upon local circumstances and the typ e and category of road. But, normally, the team will consist of a team leader, an assistant and a driver. When traffic densities are high, an additional assistant is useful for safety purpose s and to help direct traffic. The following are the duties of the team members:  Team leader – has overall responsibility for the work of the team and, in partic ular, for all safety aspects; should carry out the detailed measurements and recording of def ects; should normally push the measuring wheel along the left-hand edge of the carriageway; ma ke any notes on any safety defects or other urgent actions which should be brought to the at tention of the engineer 5mm 25mm 150mm 30mm 5 10 15 20 Wedge made from aluminium Top of wedge showing wheel-track rutting markings Straight-edge made from aluminium channel 2 metres Alternative designs with handles Straight-edge with fixed handles Straight-edge with folding handle Wedges with handles 5 Figure B.2 Deformation gauge (straight-edge and wedge) 72TRL Overseas Road Note 1, 3rd edition  First assistant – will work on the opposite side of the carriageway to the team lead er and assist with the detailed measurement of defects; should carry the deformation g auge and make the measurements of rut depth  Driver – is responsible for transporting the team to site; should drive the vehicle on the carriageway immediately between the traffic and the inspection team, and switch on its hazard warning lights  Second assistant – should be used on heavily trafficked roads; principal task should be to warn team members of approaching traffic, but can also assist with measuremen t  Labourers – may be used to assist with surveys or to carry equipment; when on s ite, they must wear safety jackets and obey the same safety rules as other team members ; note that having too many members can hinder safe working Visual inspection procedure B.17 In a visual inspection, defects are measured by hand within each section of r oad. B.18 Before leaving the office, the team leader should obtain a list of secti ons to be inspected. The team leader should check personally that all of the inspection equipment needed has been collected together and loaded in the vehicle. They should ensure that the vehicle has sufficient fuel. B.19 Once on site, the team leader must establish the start of the length to be inspected. Each section is normally identified uniquely by a label and a written descrip tion. B.20 The team leader sets up the measuring wheel at the edge of the carriageway a t the start of the sub-section to be inspected. The first assistant starts on the opposite side of the carriageway and carries the deformation gauge. The driver places the vehicle on the carr iageway, with hazard lights flashing, behind the team leader. The driver should be ready to follow i mmediately behind the team as they progress along the section. It is helpful if a second assistant can be made available to work with the team leader. Once on site, the team leader records details of t he section label, and measures the width of the carriageway and shoulders or footway. B.21 The team then walk along the section, identifying, measuring and recordi ng defects. Normally, the start and end chainage of defects are recorded but, in add ition, the team should pause every 100 metres to check that defects currently recorded are still vali d. B.22 At the end of the section, the measured length at the section end is record ed. The team leader then checks that all details have been recorded correctly and signs-off on the paper form. The team then drive to the next section. Defects Defects to be recorded B.23 Table B.5 shows the defects to be recorded. In addition, gravel thicknes s can be recorded for gravel-surfaced roads. Accuracy B.24 Correct and accurate recording in the field is essential if the results of inspections are to be useful and to avoid unnecessary effort in checking errors later. When co mpleting the paper forms, legible recording of data is vital. Chainages and lengths should be reco rded to the nearest whole metre, and widths should be recorded to the nearest 0.5 metre. Rut depth should be measured to the nearest millimetre. Defect measurement B.25 The measuring wheel is run along the left-hand edge of the carriageway t o give a continuous measurement of chainage within each sub-section. Difference in chainage measurements can be used to determine the length of any particular defect. Widths are measur ed at the start and finish of the defect using a tape measure. Where there are many defective areas, i t may be helpful to mark them out with chalk to assist measurement. 73 TRL Overseas Road Note 1, 3rd edition B.26 Particular care should be taken when measuring rut depth on the far side of the carriageway from the vehicle. Whilst the measurement is being taken, other team memb ers should keep a look out for traffic. These measurements should be taken as quickly as possib le. B.27 The following should be noted:  For cracking and ravelling, defects of less than one metre in length and 0.5 metres wide should be ignored.  Cracking is easier to identify when looking into the sun.  Ravelling should only be recorded when the amount of stone loss is great er than the amount of stone remaining, within that particular area.  All pot-holes should be recorded; small pot-holes should be recorded wit h a minimum size of 0.5m x 0.5m.  Edge deterioration of less than one metre in length should be ignored.  A note should be made on the form where fatting-up, bleeding or major sh oving occur on bituminous carriageways. Other defects B.28 If during the course of an inspection, anything is identified that should b e brought to the immediate attention of the engineer, it should be noted. Examples might be:  Road signs, retaining walls or guard rails in a dangerous condition.  Water ponding on the road, or a blocked drain.  Dangerous step at the edge of the carriageway. If inspectors find dangerous debris on the carriageway, they should remo ve it. The reverse side of the inspection form can be used for recording notes. A note should also be made when there are no defects on a section. In such cases, depending on the method of data rec ording, a paper form should still be submitted. Table B.5 Defects to be recorded Asphalt-surfaced pavements Jointed-concrete pavements Off-road features Ravelling. M inor cracking. Major shoving. Major cracking, scaling or fretting. Pot-holes. Joint defects. Edge deterioration. Slab faulting. Rutting. Worn road markings. Cracking. Worn road markings. Kerb defects Verge:  Vegetation growth (‘grass’).  Deformation and scour. Footway trips Side drains:  Silted or blocked.  Scoured or damaged. Culverts:  Silted or blocked.  Scoured or damaged. Damaged guard rails. Damaged retaining walls. Dirty, damaged or missing road signs. 74TRL Overseas Road Note 1, 3rd edition Examples of visual inspection procedure B.29 Examples are given in the following sections of recording the defects oc curring in four groups:  Asphalt-surfaced pavements.  Jointed-concrete pavements.  Gravel roads.  Off-road features. B.30 In each case, the inspections start off in the same way. Section details an d the date are recorded on the form. The measuring wheel is set to zero and set up at t he start of the section on the left-hand edge of the carriageway (for traffic driving on the left). C arriageway and shoulder widths are measured with a tape, or with a second measuring wheel, if available . A new visual inspection form is used for each section. If there is insufficient space on a form to record all defects, then an additional form should be used, numbering it as ‘Page 2’ in the to p right-hand corner. B.31 In all cases, when the inspection of the section has been completed, the se ction length is recorded, and the inspection form is checked by the team leader and sign ed off. At the end of the survey, visual inspection forms are returned to the office for review by the maintenance engineer. Visual inspection of asphalt-surfaced pavements B.32 An example of a typical defective bituminous section is shown in Figure B.3 . In this example, defects of cracking, ravelling, edge deterioration and rutting are shown. B.33 An example of an inspection form to record the defects illustrated in Figur e B.3 is shown completed in Figure B.4. Many other inspection forms have been devised a nd used successfully but in this form, two columns are provided for the recording of cracking and ravelling, and one column each is provided for the recording of pot-holes, edge deterioration and rut depth. The form is divided vertically into pairs of rows. The form is filled in from the bo ttom-up. The lower left column of each pair of rows is used to record the start and end chainage s of the occurrence of the defect. In the case of cracking and rutting, the top right column of eac h pair of rows is used to record the width of the defective area. The top left column of each of t he pairs of rows is then used to calculate the difference in the chainages. Thus, entry onto the form progresses gradually up the page as the survey moves along the road. In the case of cracking and rav elling, a second column is provided if the first proves insufficient. B.34 The inspector checks for any defects that are present at the start of th e section. In this case, the following defects are present:  Cracking in two locations.  Edge deterioration left. In the case of cracking: i) the numeral ‘0’ chainage is entered i n the bottom left (‘Length’) column of the bottom pair of rows, and the width of 0.5 metres is entered in th e top right column of this pair of rows; ii) the numeral ‘0’ chainage is entered in the bott om left (‘Length’) column of the next pair of rows, and the width of 4.0 metres is entered in the top right co lumn of this pair of rows. In the case of edge deterioration left, the numeral ‘0’ chainage is e ntered in the bottom of the ‘Chainage’ column under the appropriate heading on the form. No wi dth is recorded for the edge deterioration. Note that the end-chainage figures will be recorded later . B.35 Rut depth is recorded at regular intervals e.g. every 100 metres. Rut depth is measured for the outer wheel track on both the left and right-hand sides of the carriagew ay. The greater of these is the value recorded on the form together with the chainage. B.36 The inspector pushes the measuring wheel along the road edge and looks f or other defects starting, or existing defects stopping. Ravelling starts on the right-ha nd side of the road at Chainage 20, so this chainage figure (20) is recorded on the form under this heading. A width of 0.5m is also recorded. 75 TRL Overseas Road Note 1, 3rd edition 200 180 120 100 95 90 80 30 20 0 Edge deterioration Edge Not to scale Left shoulder shoulder Right Carriageway Chainage Ravelling Cracking deterioration B.37 At Chainage 30, both the left edge deterioration and the 0.5m wide cracking stop. The chainage value (30) is recorded in the appropriate column immediately above the start chainage, as shown. B.38 The in spector continues along the road. At Chainage 80, the ravelling stops. T his chainage value (80) is recorded above the start chainage for the defect, as sho wn on the form. B.39 At C hainage 90, edge deterioration left starts, and a further area of cracki ng starts. The chainage value (90) is recorded for each of these defects, and the wid th of cracking is recorded as 0.5 metres. B.40 At Chainage 95, the four-metre wide cracking stops. The chainage value (95 ) is recorded immediately above the start value (0). Figure B3 Example of a defective sub-section 76TRL Overseas Road Note 1, 3rd edition Figure B4 Example of a completed visual inspection form for asphalt-surf aced pavements District: Date: Section: Sub-section: Length: Width: metres metres Cracking Ravelling Pot-holesEdge deterioration Rut depth Length Length Length Length Length Width Width Width Width Width Chainage Chainage Chainage (m) (m) (m) (m) (m) (m) (m) (m) (m) (m) (m) (m) (m) Si gned……………………………………………… ..Inspector Left Right Asphalt-surfaced pavement condition survey 30 0.5 120 90 95 4.0 95 0 30 0.5 30 0 80 2.0 180 100 60 0.5 80 20 110 200 90 30 300 A.N. Inspector Depth (mm) Central A0102 225 13 October 2003 3 6.5 77 TRL Overseas Road Note 1, 3rd edition B.41 The measurement process continues as the section is walked by the inspec tors, continuing to record the start and finish of all other defects. When the end of the se ction has been reached, the measured length of the section is recorded on the form, and the carriage way width is measured and recorded. Note that, when carrying out the inspection, entries on the fo rm should be cross-checked with defects on the road every 100 metres. B.42 For each defect recording on the form, the start chainage is subtracted from the end chainage to give the length of defect which is entered in the next available box under the ‘Length’ heading. Visual inspection of jointed-concrete pavements B.43 The recording of defects on concrete roads is much more straightforward than for bituminous roads. Entries consist of simple counts of defective joints or defective slabs. As each occurs, it can be checked off on the inspection form as shown in the example in Figure B.5. At the end of the section, the totals are added for each defect. B.44 For concrete pavements without joints, it should be assumed that section s are divided into ten-metre lengths, each of which is treated as though it were a slab for measurement purposes. In such cases, no joint defects will be recorded. Visual inspection of gravel roads B.45 Visual inspection of gravel roads can be used to identify the need for r egravelling. An estimate can be made of the thickness of gravel on the road by examining pot-holes or by digging a small hole in the road surface until subgrade is reached and probing the depth with a measuring tape. Material should then be replaced and compacted with a hand tamper or punner. Ideally, thicknesses should be measured immediately after grading. But, in view o f the difficulty of timing such measurements and the need to carry out surveys on a routine basis, the following approach may be more appropriate. The survey team should take measurements on eac h sub-section or at 200-metre intervals along the road. At each survey point, the team shoul d identify any obvious ruts and should dig two holes: one in the rut and the other at the peak betwe en ruts. The gravel thickness should be recorded as the average of the two measurements, as shown in Figure B.6. Visual inspection of off-road features B.46 The recording of defects for the features of kerbs, footways, shoulders, side drains, guard rails and retaining walls all involve the measurement of defective lengt h. An example of how the visual inspection form is completed for these is shown in Figure B.7. B.47 As the insp ector progresses along the section, it is observed that, at Chainage zer o, the left-hand side drain is silted-up and there is high vegetation growth on the left-h and shoulder. A zero is entered in the appropriate columns at the bottom of the form. B.48 Continuing along the road, at Chainage 20, damage has occurred to the le ft-hand guard rail: the value ‘20’ is entered into the appropriate column. The guard-r ail damage finishes at Chainage 70, and this value is entered on the form. The total length of damaged g uard rail can now be found by subtracting the start and finish chainages to give the length of 50 m etres, which is entered on the form in the appropriate column. B.49 At Chainage 75, both the right-hand shoulder and side drain start to become scoured: the value ‘75’ is entered into each of these columns. The scouring, in both cases, stops at Chainage 90, so this value is entered, and the length of scour determined by subtract ing the chainage values in the same way as was done earlier for guard rails. This shows that 15 met res of scour is present on both the right-hand shoulder and in the side drain: these values are ent ered on the form. B.50 Other values are entered in a similar way on the form as the road inspec tion proceeds. Note that, in the case of the left-hand side drain, there is a further sectio n of siltation, 70-metres long, and a section of scour that is 15-metres long. These are added to give a tot al length of 195 metres in the total box at the bottom. Other values are transferred to the totals box as shown. The siltation of the side drain from the start of the section stops at Chainage 125, and the high vegetation stops at Chainage 210. 78TRL Overseas Road Note 1, 3rd edition B.51 Total length of defects under each heading are recorded at the bottom of this part of the form. For example, in the case of side-drain siltation, the values 125 and 70 are added to give a total defective length of 195 metres. B.52 As any culverts are reached during the survey, they are inspected for being silted or blocked, or being scoured or damaged. If a culvert is defective, the box is checked. In the example in Figure B.5, two culverts are silted or blocked and these entries are shown on the form, with the total number of defective culverts on the right. B.53 A m anual note is made of any damage to road signs, road markings, warning a nd information signs, traffic bollards, marker posts, etc, in the ‘Sign report’ box. 79 TRL Overseas Road Note 1, 3rd edition A.N. Inspector Central 13 October 2003 C359 7 225 6.5 District: Date: Section: Length: Width: metres metres Joint defects Minor cracking Major cracking, scaling or fretting Signed…………………………………………… …..Inspector Slab faulting Jointed-concrete pavement condition survey Sub-section: Figure B5 Example of a completed visual inspection form for jointed-conc rete pavements 80TRL Overseas Road Note 1, 3rd edition 1. Measurement of gravel thickness on recently graded road 2. Measurement of gravel thickness on deteriorated road with four wheelpaths 3. Measurement of gravel thickness on deteriorated road with two wheelpaths Figure B6 Measurement of gravel thickness 81 TRL Overseas Road Note 1, 3rd edition District: Date: Section: Sub-section: Shoulder/footway width: metres metres Signed…………………………………………… …..Inspector Off-road features condition survey Kerb Kerb Footway Shoulder Footway Shoulder Scour Grass Scour Side drain SiltedScour Side drain Silted Scour Grass Retaining wall Guard rail Guard rail Retaining wall Left Right Shoulder/footway width: Culverts Silted/blocked Scour/damage Sign report A.N. Inspector Central 13 October 2003 C2214 2 2.0 2.5 50 70 20 50 1950 125 125 140 210 70 125 14015 15 210 0 210 210 1575 90 15 1575 90 15 2 School sign damaged at Ch190 Figure B7 Example of a completed visual inspection form for off-road fea tures 82TRL Overseas Road Note 1, 3rd edition Appendix C: Traffic counts Manual counts C.1 The equipment required for manual counting comprises a supply of pre-pri nted forms, pencils and clip-boards. A shelter from sun or rain may be required. At low traffic volumes, the work is not demanding and the main problem is likely to be ensuring that the enumerators stay on the job. Unscheduled visits by the engineer or a senior supervisor may b e necessary to secure discipline and attention to the work. If the proportion of heavy vehicle s in the traffic flows is expected to be high, classified counts may be necessary. Automatic counters C.2 Cheap and reliable automatic traffic counters are available for recordin g total numbers of pairs of axles. These can be used to supplement manual counts or to coun t for periods of more than one day on low-volume roads. The equipment normally consists of a small rubber tube fixed across the road and attached to a pneumatic counter. When vehicles drive over t he tube, it is compressed and a pulse of air triggers the counter. The instrument records one coun t for the passage of two axles. These traffic counters need careful adjustment to ensure that bic ycles, motorcycles and pedestrians are not counted, and that heavy or fast vehicles are not ‘ double-counted’. Provided that they are checked regularly and the rubber tube replaced when it is damag ed, their use is recommended for road maintenance management purposes. C.3 Buried loop detectors can be used instead of pneumatic tubes, and are ge nerally more reliable. However, their permanent installation will not normally be jus tified solely for traffic counts for maintenance purposes. C.4 The maintenance engineer should select staff to be trained in the instal lation and use of counters, and to be responsible for their checking and maintenance. Arra ngements should be made for the daily inspection of the counter and recording of the counter rea ding. In some locations, automatic counters may be subject to theft or damage. The counters thems elves can be protected by lockable cabinets attached to solid objects, but the tubes cannot be eff ectively protected from deliberate interference. When this is experienced and regular inspection is not sufficient to prevent it, automatic counters of this type should not be used. Moving observer counts C.5 Moving observer counts can be carried out by the maintenance engineer or supervisor in the course of personal inspections. A hand-tally can be used to record the n umber of vehicles. The flow can be estimated from the expression: () / qxyt =+ where q= total flow in both directions in time t x = number of vehicles met (i.e. travelling in the opposite direction) y = number of vehicles that overtake the observer minus the number the obser ver overtakes t = journey time C.6 This expression assumes that flows in each direction are equal. If the o bserver can drive so that the number of vehicles that overtake the observer are the same as the nu mber the observer overtakes (this can usually be achieved at low traffic volumes), the expression becomes: / qxt = C.7 Counts of this type are useful as a cross-check on static counts. They c an also be used to assess the extent of variations in flow from day-to-day, or between one season and another. 83 TRL Overseas Road Note 1, 3rd edition Frequency and duration of counts C.8 Where there are likely to be high daily or seasonal variations, the freq uency or duration of counts should be increased from that recommended in Section 4. Daily var iation is often affected by local market days, which may account for a high proportion of annual tra ffic on low-volume roads. These may be allowed for by making two counts, one on a market day and one on a non-market day. Where seasonal variation is high, a count should be carried out during e ach main climatic and/or agricultural season. This enables the effect of seasonal rainfall and va riations in agricultural activity (especially during and just after harvest-time, when traffic f lows usually show a marked increase) to be taken into account. Counts extending over 16 hours (fr om 6 am to 10 pm) will usually be adequate but, in some countries where traffic is heavy at nig ht, counts should extend over 24 hours. Estimation of AADT from counts C.9 The estimation of average annual daily traffic should take account of th e factors noted above. The recommended procedure is demonstrated in the example in Box C.1. Box C.1 Estimation of AADT from counts Counts were taken near a village that has a market every seven days. The wet season lasts for about four months and the dry season eight months. 1. Two 16-hour counts were taken at the end of the dry season (low level o f agricultural activity) Count on market day = 73 vehicles Count on non-market day = 21 vehicles 2. Two 16-hour counts were taken at the end of the wet season (harvest tim e) Count on market day = 94 vehicles Count on non-market day = 48 vehicles For this example of a seven day traffic cycle, the average daily traffic is calculated for each season as follows. Average daily traffic (dry season): Tdry = ( 1/7 x 73) + ( 6/7 x 21) = 28 vehicles Average daily traffic (wet season): Twet = ( 1/7 x 94) + ( 6/7 x 48) = 54 vehicles The AADT estimate is taken as the weighted mean of the seasonal flows, c alculated thus: AADT = (8/12 x 28) + (4/12 x 54) = 37 vehicles 84TRL Overseas Road Note 1, 3rd edition 85 TRL Overseas Road Note 1, 3rd edition Appendix D: Standard forms 86TRL Overseas Road Note 1, 3rd edition 87 TRL Overseas Road Note 1, 3rd edition District: Date: Section: Sub-section: Length: Width: metres metres Cracking Ravelling Pot-holesEdge deterioration Rut depth Length Length Length Length Length Width Width Width Width Width Chainage Chainage Chainage (m) (m) (m) (m) (m) (m) (m) (m) (m) (m) (m) (m) (m) Si gned……………………………………………… ..Inspector Left Right Asphalt-surfaced pavement condition survey Depth (mm) 88TRL Overseas Road Note 1, 3rd edition 89 TRL Overseas Road Note 1, 3rd edition 90TRL Overseas Road Note 1, 3rd edition District: Period: Section: Budget: Length: Width: km/metres metres Resource requirements and cost estimate Activity: Resource Quantity Unit Rate Cost Labour Equipment Materials Sub-total Sub-total To t a l Supervisors Unskilled Skilled 1 2 3 4 5 6 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 Worker-day Worker -day Worker -day Worker -day Worker -day Worker -day Worker -day Worker -day Signed ……………………………………………… .. Sub-total 91 TRL Overseas Road Note 1, 3rd edition 92TRL Overseas Road Note 1, 3rd edition Unpaved roads This road has corrugations approximately 75 mm deep. Access has not been lost and vehicle operating costs (VOCs) are not high, but the road is dangerous to travel on at speed as control can be easily lost. Dragging can eliminate initial minor corrugations and prevent the problem getting worse, but grading is required when they reach this advanced state. (Photograph courtesy of CSIR, South Africa) Roughness This road has not been maintained for many years. Vehicles make their own routes past erosion gullies. In wet weather, access is lost. In dry weather, access is possible for only those vehicles with high ground clearance. The road should be reconstructed if reliable access is to be provided. Surface distress (loss of camber, rutting, potholes, loose materials) Appendix E: Illustrations of defects A camber is required to shed water from a carriageway. This secondary road has not been graded for a long time, the camber has been lost and potholes are developing. Each vehicle passage worsens the situation. The road should be reshaped as soon as possible. It is also noted that vegetation is encroaching onto the carriageway. Even if the camber is restored, this vegetation will retard drainage and prevent the carriageway drying out and gaining its full strength. Surface distress (loss of camber, potholes, roughness) 93 TRL Overseas Road Note 1, 3rd edition This photograph shows the level of dust that can be generated from a gravel road. The dust brings health problems to villages, affects agricultural output, is dangerous when vehicles pass or attempt to overtake and demonstrates why gravel must be frequently replenished. (Photograph courtesy of CSIR, South Africa) The fine soil on this road is dusty when dry and very slippery when wet. Gravel is hard to find in this area, so an improved surface, bituminous or non-bituminous, is recommended. Dust Longitudinal erosion is beginning to form deep gullies in this carriageway. Maintaining the camber with regular grading would have prevented this happening, although that is hard to do when the carriageway is as wide as this. Longitudinal erosion 94TRL Overseas Road Note 1, 3rd edition This road is losing its surface in long thin strips. It is probable that the spray bar on the bitumen sprayer was badly adjusted, producing narrow jets instead of overlapping sprays and leaving strips with low levels of bitumen. As a consequence the aggregate between the jets was poorly bound and has become detached by the wheels of passing traffic. In this advanced state, the road should be repaired with a surface dressing or other thin surface. Paved roads defects Ravelling The ruts and waves of asphalt caused by this severe shoving are unsafe to road users and are likely to grow further. The entire surface of the road should be removed and replaced. Surface shoving or creep Bitumen has risen to the surface of this road under the action of traffic. When the surface is smooth but aggregate is visible, the road is said to be fatting-up; when the binder rises further to form a continuous film, the road is said to be bleeding. Both conditions can be due to poor material control, low application rates of chippings, inadequate mixing, over-application of tack coat or secondary compaction of an asphalt surface. Treatment is not essential, but if a loss of skid resistance is a problem, treatment can include the rolling-in of heated aggregate or a new layer of surface dressing or asphalt. If severe, the asphalt may need to be removed before a new layer is constructed. Fatting-up or bleeding 95 TRL Overseas Road Note 1, 3rd edition This trench has been poorly reinstated. The fill material, insufficiently compacted during the reinstatement, has settled under the weight of traffic. The rut is now dangerous to vehicles. The bituminous surface has deformed and cracked, letting water into the lower layers. The rut will deepen, presenting greater danger and placing the utility buried in the trench at risk of damage. The trench should be excavated and reinstated again. Old trench opening for utility Small cracks in this thin surfacing have allowed water to enter the granular base. The base has softened and the surfacing has collapsed into the pot-hole. The pot-hole now collects water and every time a vehicle passes through, material is splashed out and the pot-hole deepens. The pot-hole is a serious hazard to road users and their vehicles and should be patched urgently. Patching involves removing all weak material, cutting the surfacing back to beyond the extent of the hole, and reconstructing the road in layers. If a pot-hole can be identified and repaired before it deepens and becomes a serious hazard, repair costs are saved and road users are not exposed to danger. The repair of this pot-hole is much simpler than that of the pot-hole in the photo above, although it is recommended that the top layer of unbound material is replaced as it may have degraded since the pot-hole opened. Pot-holes This defect is due to shoving of the base and sub-base. This shoving has resulted in a rut approximately half a metre deep which is extremely dangerous for passing traffic. An earlier repair is visible and suggests that water was allowed to enter the surface and soften the lower layers. Further investigation is likely to be required. At the very least the damaged material should be removed to the full depth of the road and the road reconstructed at this point. Major shoving 96TRL Overseas Road Note 1, 3rd edition This centre line is now barely distinguishable from other marks on the road. If drivers expect to see road markings, particularly centre lines, but fail to see them, head on or corner-to-corner impacts are more likely. Road markings should always be repainted before they become as faint as is shown here. Worn road markings The edge of this road has not broken but the shoulder material has worn away to leave a deep step which is a danger to passing vehicles and to those attempting to pull off the carriageway. The shoulder should be filled and compacted. Edge step The edge of this road is breaking, probably due to the shoulder material wearing away. Vehicles driving close to the edge may lose control and veer towards the steep drop on the right. If not repaired, the road will gradually lose width and restrict the passage of vehicles. It is necessary to open up the defect to check that the base is not damaged further into the road and then repair the road with a patch. The shoulder should also be filled and compacted. This thin surface is breaking away from the base layer. Although the step is very shallow and not dangerous, if the damage is not repaired with a small patch it will continue into the carriageway and require more extensive and costly repair. The base appears very dusty and so should be cleaned of all loose material before the repair is made. Edge damage 97 TRL Overseas Road Note 1, 3rd edition Curved or parabolic cracks normally occur at sites where tyres place high lateral forces on the surface. These sites include junctions, sharp bends and steep hills. They do not indicate major structural damage, but inadequate adhesion between base and surface, due to a poor tack coat or polished aggregate. The damaged material should be removed and a patch constructed. Cracking outside wheeltracks – parabolic crack In extreme cases large areas of surface can slip. In this photo a twenty metre length of surface along the nearside wheeltrack has slipped from the base. The defect is localised and is not at a site where high lateral forces are applied. It is likely that the surface was poorly bonded to the base over this length. A surface patch is required. Cracks can occur in many positions on a paved road, including along white lines. White areas reflect sunlight while black areas absorb it and become hotter. Materials expand and contract from day to night according to their temperature. The difference in thermal movement along the edge of a white line on a dark road causes bitumen bonds to be broken and cracks to open up. The crack should be sealed, although, because water is unlikely to enter a crack along the crown of the road, repair is not urgent and can be carried out when the line is remarked. Cracking outside wheeltracks – along white line 98TRL Overseas Road Note 1, 3rd edition This is a single jagged crack across the carriageway. Its width is greater than 3 mm and is therefore defined as a wide crack. Cracks such as this are often due to a weak longitudinal joint in an asphalt overlay or poor trench reinstatement. They may also be reflection cracks from the shrinkage of a stabilised base layer. The crack should be sealed. Unless further movement occurs, this defect is unlikely to become a serious problem. Cracking outside wheeltracks – lateral cracks This road consists of a narrow surface laid onto a wide base. It is a cost effective way of allowing high speed travel but retaining wide shoulders for slow moving or non-motorised traffic. The base is cracked, probably due to thermal movement. The crack is reflecting through the surfacing. Transverse cracks at close spacing are often caused by thermal or shrinkage movement. They are more likely in areas of high day-night temperature change. Cracks such as these should be sealed. 99 TRL Overseas Road Note 1, 3rd edition Cracking in wheeltracks Longitudinal cracks are developing in the nearside wheeltrack. They may be due to movement in the sub-grade, either swelling or settlement. The cracks should be sealed and the area monitored for surface movement. Extensive cracks may require a surface dressing. A combination of longitudinal and transverse cracks into blocks is normally due to either thermal or shrinkage movement of the upper layer or reflection of shrinkage in a stabilised base layer. The cracks are wide apart and should be sealed. Cracking outside wheeltracks – block cracks The very straight cracks across the road and between the outer and inner lane are due to poor construction techniques. The paving was not properly tied, with a stepped joint, to either the previous day’s work or the neighbouring lane. The cracks should be sealed, after which no further movement is likely to occur. 100TRL Overseas Road Note 1, 3rd edition Wheeltrack rutting This road is rutted and cracked. It is not clear whether a deforming base has caused cracks to form in the surface or cracks have allowed water to enter and weaken the base. In this advanced state it is necessary to remove the damaged material – surface and base – and construct a patch. If repairs are not made soon, pot-holes will develop. Further investigation is recommended. Wheeltrack rutting and cracking Crocodile cracking Closely spaced inter-connecting cracks are referred to as crocodile cracks. If there is no rutting, the most likely causes are poor construction of the surface layer, aged and inflexible binder, poor bond with the base layer. If the cracking is identified early, the cracks should be sealed. If the cracking has developed but is of limited extent, the affected area should be removed and patched. If the cracking has developed and is extensive, the length of road should be surfaced with asphalt or a surface dressing. If rutting is also present the road will need strengthening and detailed investigation is required. This rut has deepened. It is clear from the ridge on the right hand side that the asphalt is flowing under the action of traffic. This is referred to as ‘shoving’. The material is incapable of supporting more traffic and should be removed and replaced. It may be possible to mill and inlay a narrow strip if the rutting is present in only one wheeltrack. Shoving often occurs on steep hills or at junctions where slow moving heavy vehicles impose very heavy loads on the road surface. This photo shows a shallow rut with no cracking. It is not yet clear whether it is the surface or the lower layers that are deforming. It is recommended that a rut such as this is monitored as further deformation will indicate where the problem lies. If small cracks appear during the monitoring, they should be sealed. Continuing deformation will show that the road is not strong enough and an overlay may be required.